| UMIS Number | BG-RRP-4.032-0255-C01 |
| Project Name | "Construction of a local battery storage power station (BESS) with an installed capacity of 0.9 MW and a storage capacity of 1.8 MWh connected to a photovoltaic power plant with an installed capacity of 2,99 MW." |
| Beneficiary | 206285145 PV Rakovski LTD |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 17.02.2025 |
| Start Date | 17.02.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Предложението за изпълнение на инвестиция предвижда изграждане на локално съоръжение за съхранение на електроенергия (ЛСС) с мощност 0,9 МW и капацитет 1,8 MWh. Съоръжението ще бъде свързано към съществуваща фотоволтаична инсталация с инсталирана AC мощност 2,99 MW на кандидата "ПВ Раковски" ООД, разположена в УПИ 105578, м. “Шипа”, КККР с. Стряма, с ЕКАТТЕ 70010, община Раковски. С изграждането на системата за съхранение се цели оптимизиране на произведената електроенергия от изградения фотоволтаичен парк. Дейността е съобразена с изискванията на принципа за „ненанасяне на значителни вреди“ върху околната среда и ще допринесе за екологичния преход на страната. Енергийният обект за производство на електрическа енергия от слънчева енергия е присъединен към съответната електрическа мрежа и отговаря на приложимите изисквания относно влиянието върху околната среда. Проектът ще осигури изграждане на локално съоръжение за съхранение на електроенергия (ЛСС) като част от комбиниран проект за създаване на нова мощност за производство на електрическа енергия от слънчева енергия и мощности за съхранение. Предвидените ЛСС, както и изградените капацитети по отношение на компонента за производство на електрическа енергия, отговарят на изискването за "нова мощност". |
| Activities |
|
| Partners | None |
| Contractors | None |
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.90 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 1.80 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 2.99 , Reached amount: 0.00 |
| Total Project cost | 395 995.56 EUR |
| Grant | 197 997.78 EUR |
| Self amount | 197 997.78 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка и инсталация на ЛСС,
Estimated Amount: 323 494.37
|
| Procedure 2 |
Subject to due process: Доставка и монтаж на съоръжения за свързване на ЛСС към съоръженията на обекта, който се изгражда по комбинирания проект,
Estimated Amount: 62 377.61
|
| Procedure 3 |
Subject to due process: Извършване на дейности по проектиране,
Estimated Amount: 3 579.04
|
| Procedure 4 |
Subject to due process: Извършване на СМР за пуск в експлоатация на ЛСС,
Estimated Amount: 6 544.54
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN