Identification

UMIS Number BG-RRP-1.015-1545-C01
Project Name Building STEM environment and high-tech equipped and connected classrooms
Beneficiary 000123298 Primary School "Hristo Botev"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 30.09.2024
Start Date 30.09.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северен централен (BG32), Велико Търново (BG321), Свищов, с.Ореш

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищна СТЕМ среда и високотехнологични оборудвани и свързани класни стаи( ВОСКС): Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване., Contracted Amount: 30 537.15 , Reported Amount: 61 074.30

Participating Organizations

Partners None
Contractors
  • Contractor: A1 Bulgaria EAD, Contracted Amount*: 25 896.87 , Reported Amount**: 51 793.74
  • Contractor: SLAVOV INVEST, Contracted Amount*: 4 640.28 , Reported Amount**: 9 280.56
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 10.00 , Reached amount: 10.00

Financial Information

Total Project cost 30 842.52 EUR
Grant 30 842.52 EUR
Self amount 0.00 EUR
Total actual amounts paid 30 791.62 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN