| UMIS Number | BG-RRP-4.032-0312-C01 |
| Project Name | Construction of a Local Energy Storage System with a Capacity of 0.5 MW for an Existing Photovoltaic Installation with a Capacity of 1 MW in the Land of the Village of Krupnik, "Kostova Ornitsa" Area, by "Georesurs" Ltd. |
| Beneficiary | 811161735 GEORESURS LTD |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 10.03.2025 |
| Start Date | 10.03.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Високите цени на електроенергията, съчетани с голяма несигурност и риск на пазарите, увеличават разходите на дружеството. С оглед да се справи с това се налага дружеството да търси гъвкави и ефективни решения за справяне с трудностите. "Георесурс" ЕООД предвижда изграждане на локална система/съоръжения за съхранение на електрическа енергия с мощност 0,5 MW към съществуваща фотоволтаична инсталация с инсталирана мощност 1 MW в землището на с. Крупник. Като произведената лектрическата енергия е предимно за собствени нужди, а когато производството е по-голямо от консумацията ще се отдава в мрежата на ЕРП. Изпълнението на проектната дейност и постигането на поставените цели ще допринесе за усъвършенстване на работния процес с цел отговор на актуалните тенденции в бранша и динамиката в развитието на потребителското търсене и утвърдените нормативни изисквания към крайните продукти, ще повиши конкурентоспособността и намаление на режийните разходи. Проектът е със срок на изпълнение 18 месеца и е на обща стойност 500 000.00 лв. без ДДС. Мястото на изпълнение ще е поземлен имот с идентификатор 40052.21.26, местност "Костова Орница" по КККП на с. Крупник, общ. Симитли. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.50 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 255 645.94 EUR |
| Grant | 127 822.97 EUR |
| Self amount | 127 822.97 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Закупуване на локални съоръжения за съхранение на енергията с мощност 0,5 MW - 5 бр.,
Estimated Amount: 500 000.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN