Identification

UMIS Number BG-RRP-4.026-0597-C01
Project Name Хибридна фотоволтаична инсталация за собствени домакински нужди
Beneficiary Boris
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 07.03.2025
Start Date 07.03.2025
End Date 16.03.2026
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Враца (BG313), Мездра, с.Моравица

Description

Brief description
Хибридна фотоволтаична инсталация за собствени домакински нужди 
Състояща се от 12бр фотоволтаични панели с мощност 535W,
Хибриден инвертор 6kW с автоматично ограничаване експорта на енергия
2бр Батерии 5kW за резервиране на електроенергията 
Алуминиева конструкция за прикрепяне и насочване
Допълнително ел. табло за опроводяване
Activities
  • Activity: Доставка, монтаж и пускане в експлоатация на хибридна фотоволтаична система: Хибридна фотоволтаична инсталация за собствени домакински нужди Състояща се от 12бр фотоволтаични панели с мощност 535W, Хибриден инвертор 6kW с автоматично ограничаване експорта на енергия 2бр Батерии 5kW за резервиране на електроенергията Алуминиева конструкция за прикрепяне и насочване Допълнително ел. табло за опроводяване, Contracted Amount: 20 292.00 , Reported Amount: 10 370.36

Participating Organizations

Partners None
Contractors
  • Contractor: BV engineering Ltd, Contracted Amount*: 7 262.59 , Reported Amount**: 10 370.36
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

None

Financial Information

Total Project cost 10 370.36 EUR
Grant 7 262.59 EUR
Self amount 3 107.77 EUR
Total actual amounts paid 7 262.59 EUR
Percentage of EU co-financing 83.34 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка, монтаж и пускане в експлоатация на хибридна фотоволтаична система , Estimated Amount: 10 375.13

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN