| UMIS Number | BG-RRP-13.009-0183-C01 |
| Project Name | Installation of photovoltaic systems (PV) and electromobility for the social sphere in the municipality of Peshtera |
| Beneficiary | 000351750 PESHTERA Municipality |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 05.12.2025 |
| Start Date | 05.12.2025 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектът обединява няколко важни дейности, които ще допринесат за модернизация и устойчиво развитие на социалните услуги в община Пещера. В рамките му ще се инсталират фотоволтаични системи в два ключови социални обекта – Център за настаняване от семеен тип и Дневен център за деца и младежи с увреждания. Тези системи ще осигурят чиста електроенергия за собствена консумация, което ще намали както оперативните разходи, така и въглеродния отпечатък на социалните услуги. Освен това, проектът предвижда закупуването на електрическо превозно средство, предназначено за обслужване на социалните услуги, както и изграждането на съответната зарядна инфраструктура. Това ще подобри мобилността и ще даде възможност на екипите да предоставят по-бързо, по-екологично и ефективно социални услуги както в центровете, така и при посещенията в домовете на потребителите. Чрез комбинирането на възобновяеми енергийни източници и електрически транспорт, проектът цели не само подобряване на качеството и ефективността на социалните услуги, но и активен принос към намаляването на вредните емисии и насърчаването на устойчив начин на работа в общината. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Purchased electric vehicles and connected charging stations, each with a minimum power of 22 kW, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Number of social services with installed PV power plants with a capacity of 15 to 30 kW, Measure Unit: Number, Base Value: 0.00 , Target amount: 2.00 , Reached amount: 0.00 |
| Total Project cost | 157 688.35 EUR |
| Grant | 157 688.35 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: „Инсталиране на фотоволтаични системи (ФЕЦ) в съществуващи сгради за социални услуги, делегирана от държавата дейност по обособени позиции“:
- Обособена позиция №1 - „Доставка, монтаж и въвеждане в експлоатация на фотоволтаична система с мощност 30 kW и батерия за съхранение на енергия в Център за настаняване от семеен тип – гр. Пещера“
- Обособена позиция №2 - „Доставка, монтаж и въвеждане в експлоатация на фотоволтаична система с мощност 30 kW и батерия за съхранение на енергия в Дневен център за деца и младежи с увреждания– гр. Пещера“,
Estimated Amount: 83 004.66
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN