| UMIS Number | BG-RRP-1.007-0050-C01 |
| Project Name | "Major repair, energy efficiency measures and provision of an accessible environment of buildings of the Primary School "St. St. Cyril and Methodius - Varna" |
| Beneficiary | 000093442 VARNA MUNICIPALITY |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 16.01.2024 |
| Start Date | 16.01.2024 |
| End Date | 31.05.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектът е за осъществяване на модернизация и обновяване на образователната инфраструктура на ОУ „Свети Свети Кирил и Методий“ Варна е в пълно съответстие с приоритетите на НПВУ. С преустроиството се цели осигуряване на материална база, гарантираща здравословни и качествени условия за обучение в съвременна и ефективна среда, осигуряваща по-добри условия за учене и работа. С дейностите по изпълнение на СМР, СН и АН, ще се реализират мерките в ИП за: - Осигуряване на здравословна и благоприятна среда за провеждане на качествен и ефективен учебен процес. - Въвеждане на мерки за ЕЕ за постигане на клас на енергопотребление "А" на училищната сграда. - Привеждане на сградата в съответствие с изискванията за достъпна архитектурна среда, като се отчитат и характерните условия, при които се осъществява учебния процес. - Осигуряване на необходимите условия за последващо изграждане на училищна СТЕМ среда. През 2021/2022г. в училището се обучават 820 деца и ученици. Осъвременената и отговаряща на новите изисквания материалната база на училището са от съществено значение за създаването на благоприятна, приобщаваща среда, с цел подобряване на образователните резултати и мотивацията за учене. Промените в методиката и в процеса на обучение изискват адекватното им отразяване при създаването на нова учебна среда, която да отговаря на потребностите и тенденциите в развитието на подрастващите и предопределя в голяма степен и успешното им развитие като цяло. Обновяването на сградния фонд на образователната институция гарантира поддържане на високо качество и ефективност на цялостния образователен процес, в съответствие с изискванията на ЗПУО и „Европа 2020“, както и на релевантните поднормативни актове. Проектът допринася за изпълнение на политиката на МОН за създаване на модерна среда в образователните институции и за осъществяване на комплексната образователна реформа в страната. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Savings in annual primary energy consumption, Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 646.21 , Reached amount: 0.00 |
| Indicator 2 | Renovation and/or construction works of schools, kindergartens and student dormitories, and construction works of campuses, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 3 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 852.00 , Reached amount: 0.00 |
| Total Project cost | 2 289 832.08 EUR |
| Grant | 2 289 832.08 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 244 975.52 EUR |
| Percentage of EU co-financing | 83.47 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: "Осъществяване на авторски надзор по време на строителството на следните обекти: „Основен ремонт, въвеждане на мерки за енергийна ефективност и осигуряване на достъпна среда на сгради на ОУ „Св. Св. Кирил и Методий с идентификатори 10135.1508.37.1 и 10135.1508.37.3, находящ се в УПИ II-„за училище и трафопост“, кв. 709, по плана на 3-ти м.р., гр. Варна“ и „Пристрояване на евакуационно стълбище в сграда с идентификатор 10135.1508.37.1“,
Estimated Amount: 58 989.17
|
| Procedure 2 |
Subject to due process: "Упражняване на строителен надзор за обекти по „Основен ремонт, въвеждане на мерки за енергийна ефективност и осигуряване на достъпна среда на сгради на територията на община Варна по обособени позиции“, за проекти на Община Варна финансирани в рамките на процедура за подбор на проекти от крайни получатели BG-RRP-1.007 „Модернизация на образователна среда”, по Националния план за възстановяване и устойчивост (НПВУ) с финансиране от Механизма за възстановяване и устойчивост (МВУ),
Estimated Amount: 199 000.00
|
| Procedure 3 |
Subject to due process: „Основен ремонт, въвеждане на мерки за енергийна ефективност и осигуряване на достъпна среда на сгради на ОУ „Св. Св. Кирил и Методий с идентификатори 10135.1508.37.1 и 10135.1508.37.3, находящ се в УПИ II-„за училище и трафопост“, кв. 709, по плана на 3-ти м.р., гр. Варна“ и „Пристрояване на евакуационно стълбище към сграда ОУ „Св. Св. Кирил и Методий” /10135.1508.37.1/”, което е неразделна част от основния обект,
Estimated Amount: 5 374 153.15
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN