| UMIS Number | BG-RRP-1.015-1290-C02 |
| Project Name | Andrey Sakharov |
| Beneficiary | 000803458 MAXIM GORKY SECONDARY SCHOOL |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 26.09.2024 |
| Start Date | 26.09.2024 |
| End Date | 31.05.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС). |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors |
|
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 231.00 , Reached amount: 0.00 |
| Total Project cost | 185 905.73 EUR |
| Grant | 185 905.73 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 179 778.22 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка и монтаж на обзавеждане ,
Estimated Amount: 24 229.98
|
| Procedure 2 |
Subject to due process: Извършване на СМР,
Estimated Amount: 80 926.12
|
| Procedure 3 |
Subject to due process: Обществена поръчка предмет: ДОСТАВКА, МОНТАЖ И ВЪВЕЖДАНЕ В ЕКСПЛОАТАЦИЯ НА ТЕХНОЛОГИЧНО ОБОРУДВАНЕ ЗА ИЗГРАЖДАНЕ STEM ЦЕНТЪР В СУ «МАКСИМ ГОРКИ», ГР. СТАРА ЗАГОРА ПО ОБОСОБЕНИ ПОЗИЦИИ.,
Estimated Amount: 0.00
|
| Procedure 4 |
Subject to due process: Обществена поръчка предмет: ДОСТАВКА, МОНТАЖ И ВЪВЕЖДАНЕ В ЕКСПЛОАТАЦИЯ НА ТЕХНОЛОГИЧНО ОБОРУДВАНЕ ЗА ИЗГРАЖДАНЕ STEM ЦЕНТЪР В СУ «МАКСИМ ГОРКИ», ГР. СТАРА ЗАГОРА.,
Estimated Amount: 140 155.20
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN