Identification

UMIS Number BG-RRP-1.015-0462-C02
Project Name Building a school STEM environment at "Bratya Miladinovi" Primary School
Beneficiary 000041933 NACHALNO UCHILISHTE BRATYA MILADINOVI
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 19.06.2024
Start Date 19.06.2024
End Date 09.02.2026
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Бургас (BG341), Камено, с.Кръстина

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищна STEM среда и ВОСКС в НУ Братя Миладинови, с. Кръстина: Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване., Contracted Amount: 30 677.51 , Reported Amount: 61 348.88

Participating Organizations

Partners None
Contractors
  • Contractor: Parketen svyat LTd, Contracted Amount*: 2 779.21 , Reported Amount**: 5 558.42
  • Contractor: Planiks Ltd, Contracted Amount*: 19 173.45 , Reported Amount**: 38 346.88
  • Contractor: NERO 1 LTD, Contracted Amount*: 1 985.01 , Reported Amount**: 3 970.02
  • Contractor: Deli Marker Ltd, Contracted Amount*: 6 736.78 , Reported Amount**: 13 473.56
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 16.00 , Reached amount: 16.00

Financial Information

Total Project cost 30 930.06 EUR
Grant 30 930.06 EUR
Self amount 0.00 EUR
Total actual amounts paid 30 930.07 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN