Identification

UMIS Number BG-RRP-1.015-0313-C02
Project Name Building a school STEM environment and HECC in OU "SV.SV. KIRIL I METODIY"
Beneficiary 000082570 OU "SV.SV. KIRIL I METODIY"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 26.04.2024
Start Date 26.04.2024
End Date 20.10.2025
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Североизточен (BG33), Варна (BG331), Долни чифлик, с.Голица

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищна STEM среда и ВОСКС в ОСНОВНО УЧИЛИЩЕ "СВ.СВ. КИРИЛ И МЕТОДИЙ" : Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване. , Contracted Amount: 30 616.47 , Reported Amount: 61 232.98

Participating Organizations

Partners None
Contractors
  • Contractor: „Era Build 2020“ Ltd, Contracted Amount*: 11 493.90 , Reported Amount**: 22 987.80
  • Contractor: UNION INTERACTIVE LTD., Contracted Amount*: 19 122.58 , Reported Amount**: 38 245.18
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 10.00 , Reached amount: 10.00

Financial Information

Total Project cost 30 871.60 EUR
Grant 30 871.60 EUR
Self amount 0.00 EUR
Total actual amounts paid 30 871.60 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN