| UMIS Number | BG-RRP-1.015-2069-C01 |
| Project Name | Construction of a STEM environment and HECC for more effective and innovative teaching and learning in PGT "Mihalaki Georgiev" in Vidin. |
| Beneficiary | 000152182 PG PO TURIZAM "MIHALAKI GEORGIEV" |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 06.11.2024 |
| Start Date | 06.11.2024 |
| End Date | 31.05.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС). |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 117.00 , Reached amount: 0.00 |
| Total Project cost | 129 090.48 EUR |
| Grant | 129 090.48 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 107 135.60 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Договор за възлагане на строително-монтажни работи /СМР/,
Estimated Amount: 54 208.08
|
| Procedure 2 |
Subject to due process: Договор за доставка и монтаж на специализирано оборудване по проект BG-RRP-1.015 - " Училищна STEM среда и ВОСКС в ПГТ "М. Георгиев" - гр. Видин,
Estimated Amount: 45 408.67
|
| Procedure 3 |
Subject to due process: Доставка и монтаж на обзавеждане по проект BG-RRP-1.015 - " Училищна STEM среда и ВОСКС в ПГТ "М. Георгиев" - гр. Видин,
Estimated Amount: 24 892.63
|
| Procedure 4 |
Subject to due process: Доставка на софтуерпо проект BG-RRP-1.015 - " Училищна STEM среда и ВОСКС в ПГТ "М. Георгиев" - гр. Видин,
Estimated Amount: 156.00
|
| Procedure 5 |
Subject to due process: Доставка, монтаж и въвеждане в експлоатация на оборудване в изпълнение на проект BG-RRP- 1.015 - "училищна STEM среда“ за изграждане на STEM среда и ВОСКС в ПГТ "Михалаки Георгиев" - гр. Видин“, по обособени позиции,
Estimated Amount: 96 056.43
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN