| UMIS Number | BG-RRP-4.032-0234-C01 |
| Project Name | Construction of an electricity storage system for a photovoltaic installation located in land 12259.1008.441, Vratsa |
| Beneficiary | 204462045 "V-HERB STORE" Ltd. |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 09.11.2025 |
| Start Date | 09.11.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проекта включва изграждането на локално съоръжение за съхранение на електроенергия(ЛСС) с мощност 1,8 MW, паралелно свързан към фотоволтаична инсталация с AC мощност 3,75 MW, разположена в поземлен имот 12259.1008.441, по КР на град Враца с GPS координати: 43°13'22.6"N 23°31'32.3"E. В имот 12259.1008.441 e изградена фотоволтаична централа за производство на електроенергия от възобновяем източник с инсталирана мощност от 3,75MW и разполага с 2 бр. трансформаторни постове, преобразуващи напрежението от 0,8kV в 20kV. Избраната система за съхранение на електроенергия е с мощност от 1,8 MW, като разполага с трансформатор, преобразуващ напрежението в 20kV, което позволява свързването ѝ в паралел със съществуващата система. За гарантиране на продължителност на работа и продължителен живот на съоръжението, е избрана батерия с общ капацитет от 3,727 MWh, което гарантира продължителност на работа на съоръжението от минимум 2 часа при цикъл на разреждане, при номинална мощност на инверторната част на ЛСС – съответно скоростта на зареждане и разреждане на батерията е C/2. За зареждане на системата следва да се използва електроенергия минимум 75% генерирана от фотоволтаичния парк на годишна база, към който е свързана. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 1.80 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 3.73 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 3.75 , Reached amount: 0.00 |
| Total Project cost | 1 748 618.24 EUR |
| Grant | 874 309.12 EUR |
| Self amount | 874 309.12 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: изграждането на локално съоръжение за съхранение на електроенергия(ЛСС) с мощност 1,8 MW и капацитет на съхранение 3,727 MWh,
Estimated Amount: 3 420 000.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN