| UMIS Number | BG-RRP-4.020-0025-C02 |
| Project Name | "Energy-efficient reconstruction of the building of the "Ana Maimunkova" chitalishte, Voden village, Bolyarovo municipality |
| Beneficiary | 000970051 Bolyarovo Municipality |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 28.05.2024 |
| Start Date | 28.05.2024 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектното предложение предвижда изпълнение на мерки за енергийно обновяване на НЧ "Ана Маймункова" , намираща се в село Воден, община Болярово на улица „Н. Пехливанов“ №69. Проектът предвижда подмяна на дограмата на сградата, топлоизолация на стените и покрива, оптимизация на осветителната система, изграждане на термопомпи-инверторни мултисплит системи за отопление и охлаждане. Проектът попада в компонент 2 на процедурата за набиране на проектни предложения. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium |
|
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Намаляване на емисиите на парникови газове, Measure Unit: тонове CO2 екв., Base Value: 0.00 , Target amount: 123.13 , Reached amount: 0.00 |
| Indicator 2 | Completed energy-efficiency renovation of non- residential buildings – renovated surface of public buildings (sub-measure 2), Measure Unit: m2, Base Value: 0.00 , Target amount: 904.00 , Reached amount: 904.00 |
| Indicator 3 | Reduction of annual primary energy consumption, Measure Unit: kWh/година, Base Value: 0.00 , Target amount: 582 619.64 , Reached amount: 0.00 |
| Indicator 4 | Energy efficiency renovation of non-residential buildings, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Total Project cost | 506 173.01 EUR |
| Grant | 477 888.34 EUR |
| Self amount | 28 284.67 EUR |
| Total actual amounts paid | 460 895.42 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: изготвяне на независима експертна оценка,
Estimated Amount: 2 556.46
|
| Procedure 2 |
Subject to due process: Изготвяне на обследване за ЕЕ и сертификат за ЕЕ, разходи за ТО и технически паспорт.,
Estimated Amount: 4 381.73
|
| Procedure 3 |
Subject to due process: Изпълнение на строителен надзор,
Estimated Amount: 31 911.43
|
| Procedure 4 |
Subject to due process: Инженеринг - изпълнение на проектиране, авторски надзор и строително-ремонтни дейности.,
Estimated Amount: 377 589.05
|
| Procedure 5 |
Subject to due process: Консултантски услуги, свързани с управление и осигуряване на публичност по проекта,
Estimated Amount: 7 834.23
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN