UMIS Number | BG-RRP-1.007-0015-C01 |
Project Name | Modernization and implementation of measures to increase the energy efficiency of buildings of the Second Secondary School "Professor Nikola Marinov" |
Beneficiary | 000875920 OBSHTINA TARGOVISHTE |
Funding | RRF ==> Recovery and Resilience Plan |
Date of the Contract/Order | 23.02.2024 |
Start Date | 23.02.2024 |
End Date | 23.02.2026 |
Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
Location of Performance |
|
Brief description |
По проекта се предвижда основен ремонт, реконструкция на цялата сграда на Второ СУ „Проф. Никола Маринов“, конструктивно укрепване, мерки за енергийна ефективност на учебните сгради с предвиждане на конкретни мерки водещи до намаляване на енергопотреблението при повишаване комфорта на обитаване, ремонт на покрива, подмяна на дограма, изграждане/подмяна на ВиК инсталации, инсталации за енергия, отопление, вентилация, охлаждане, ремонт на санитарни възли, оптимизиране и естетизиране на вътрешното пространство в образователната институця, включително в контекста на COVID-19 и бъдещи пандемични/извънредни ситуации за намаляване на струпването на учащи, изграждане на инсталации за използване на алтернативни източници на енергия, и други строително-монтажни работи за осигуряване на цялостен обновен облик на образователната институция както отвън, така и отвътре и за спестяване на енергийни, водни и други ресурси, включително прилежащото дворно място. |
Activities |
|
Partners | None |
Contractors |
|
Subcontractors | None |
Members of the Consortium | None |
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
Indicator 1 | Savings in annual primary energy consumption, Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 674.68 , Reached amount: 0.00 |
Indicator 2 | Finalisation of renovation of schools and kindergartens, Measure Unit: Брой, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
Indicator 3 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: лица, Base Value: 0.00 , Target amount: 1 280.00 , Reached amount: 0.00 |
Total Project cost | 4 261 187.43 BGN |
Grant | 4 261 187.43 BGN |
Self amount | 0.00 BGN |
Total actual amounts paid | 1 388 063.20 BGN |
Percentage of EU co-financing | 83.47 % |
None | |
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
Procedure 1 |
Subject to due process: „Инженеринг – (проектиране, строителство и авторски надзор) при изпълнение на проект "Основен ремонт, обновяване и модернизация на сградата на Второ средно училище „Професор Никола Маринов“ ,
Estimated Amount: 3 450 626.67
|
Procedure 2 |
Subject to due process: Строителен надзор,
Estimated Amount: 0.00
|
Notes:
All amounts are in Bulgarian lev (BGN) / 1 EUR = 1,95583 BGN