| UMIS Number | BG-RRP-1.011-0020-C02 |
| Project Name | "Major repair and implementation of energy efficiency measures of the dormitory building at Vasil Levski University of Applied Sciences, Apriltsi" |
| Beneficiary | 000291627 OBSHTINA APRILTSI |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 06.12.2023 |
| Start Date | 06.12.2023 |
| End Date | 31.05.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Основен ремонт на сградата на общежитието към СУ "Васил Левски" гр. Априлци с цел подобряване на енергийната ефективност на сградата, намаляване на разходите за енергии и подобряване на условията на живот. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Finalisation of renovation activities in student dormitories, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Indicator 2 | Savings in annual primary energy consumption, Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 390.61 , Reached amount: 390.61 |
| Indicator 3 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 71.00 , Reached amount: 71.00 |
| Total Project cost | 1 168 676.83 EUR |
| Grant | 1 168 676.83 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 1 143 297.91 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: “Основен ремонт и въвеждане на мерки за енергийна ефективност на сграда- общежитие към СУ”Васил Левски“ , гр.Априлци по проект № BG-RRP-1.011-0020, финансиран по Оперативна програма „Национален план за възстановяване и устойчивост”,
Estimated Amount: 860 429.73
|
| Procedure 2 |
Subject to due process: „Доставка и монтаж обзавеждане за общежитие към СУ „Васил Левски” гр.Априлци по проект № BG-RRP-1.011-0020 „Основен ремонт и въвеждане на мерки за енергийна ефективност на сграда на общежитие към СУ”Васил Левски” , финансиран по Оперативна програма „Национален план за възстановяване и устойчивост”,
Estimated Amount: 44 062.63
|
| Procedure 3 |
Subject to due process: „ИЗРАБОТВАНЕ НА ИНВЕСТИЦИОНЕН ПРОЕКТ ВЪВ ФАЗА „ТЕХНИЧЕСКИ” ЗА ОБЕКТ- „ОСНОВЕН РЕМОНТ И ВЪВЕЖДАНЕ НА МЕРКИ ЗА ЕНЕРГИЙНА ЕФЕКТИВНОСТ НА СГРАДA ОБЩЕЖИТИЕ КЪМ СУ "ВАСИЛ ЛЕВСКИ" ГР. АПРИЛЦИ",
Estimated Amount: 22 496.84
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN