| UMIS Number | BG-RRP-3.006-0532-C01 |
| Project Name | Instalation of new PV for own consumption in combination with battery |
| Beneficiary | 103869642 Dinamo - Rusev Ltd |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 10.11.2023 |
| Start Date | 10.11.2023 |
| End Date | 01.04.2025 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
Основната дейност на „Динамо – Русев“ ЕООД е свързана с проектиране и изработка на ел. инсталации, ремонт на електродвигатели и генератори, силови трансформатори до 1000 kVA. Дружеството имат почти 20 години опит и разполага с квалифицирани и добре подготвени специалисти. Проектът третира изграждане на 80 kW фотоволтаична инсталация на покрив, в комбинация с 81,92 kWh батерия за съхранение на енергия. По този начин ще постигнем промяна в модела на доставка на електроенергия и ще намалим бъдещите разходи за електроенергия. Инвестиция ще доведе също до постигне на положителни икономически, финансови и екологични ефекти. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Additional operational capacity installed for renewable energy, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.08 , Reached amount: 0.08 |
| Indicator 2 | Enterprises supported (of which small – including micro, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Indicator 3 | Capacity of installed storage facilities, Measure Unit: Number (kW), Base Value: 0.00 , Target amount: 81.92 , Reached amount: 81.92 |
| Total Project cost | 122 328.74 EUR |
| Grant | 61 164.37 EUR |
| Self amount | 61 164.37 EUR |
| Total actual amounts paid | 61 164.37 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Изграждане на фотоволтаична система за собствено потребление в комбинация с батерии,
Estimated Amount: 122 710.05
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN