Identification

UMIS Number BG-RRP-1.015-0593-C02
Project Name Building a school STEM environment and HECC in “Professor Doctor Asen Zlatarov” Primary School
Beneficiary 000607566 “Professor Doctor Asen Zlatarov” Primary School
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 22.08.2024
Start Date 22.08.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Смолян (BG424), Смолян, гр.Смолян

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищна STEM среда и ВОСКС във ВТОРО ОСНОВНО УЧИЛИЩЕ "ПРОФ.Д-Р АСЕН ЗЛАТАРОВ" : Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване. , Contracted Amount: 127 370.28 , Reported Amount: 91 113.76

Participating Organizations

Partners None
Contractors
  • Contractor: NEW IV LTD., Contracted Amount*: 26 922.30 , Reported Amount**: 0.00
  • Contractor: VALI COMPUTERS LTD., Contracted Amount*: 41 656.99 , Reported Amount**: 41 656.99
  • Contractor: VT TRADE LTD., Contracted Amount*: 6 875.40 , Reported Amount**: 6 875.40
  • Contractor: „Era Build 2020“ Ltd, Contracted Amount*: 28 109.14 , Reported Amount**: 14 371.98
  • Contractor: ELGRUP - 51 Ltd., Contracted Amount*: 55 172.76 , Reported Amount**: 28 209.39
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 54.00 , Reached amount: 0.00

Financial Information

Total Project cost 128 643.98 EUR
Grant 128 643.98 EUR
Self amount 0.00 EUR
Total actual amounts paid 91 873.02 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и гаранционно обслужване на оборудване за изграждане на училищна STEМ среда и ВОСКС във ВТОРО ОУ „Проф. д-р Асен Златаров“ , финансирано по проект BG-RRP-1.015 "Училищна STEM среда" , Estimated Amount: 43 241.71
  • Differentiated position 1: Доставка, монтаж и гаранционно обслужване на компютърно оборудване и периферия за STEM център и ВОСКС
    Contractor: VALI COMPUTERS LTD.
    Contract total funded value: 41 656.99

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN