| UMIS Number | BG-RRP-1.007-0125-C01 |
| Project Name | "RENEWAL OF THE INFRASTRUCTURE AND MEASURES TO INCREASE ENERGY EFFICIENCY, REPAIR AND DELIVERY OF EQUIPMENT AND FURNISHINGS OF THE BUILDING OF SU "CHRISTO SMIRNENSKI" - TOWN OF KOYNARE" |
| Beneficiary | 000414154 RED BEACH MUNICIPALITY |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 22.12.2023 |
| Start Date | 22.12.2023 |
| End Date | 31.05.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектното предложение предвижда извършване на строително монтажни работи за цялостен обновен облик на СУ "Христо Смирненски" - гр Койнаре“ и за постигане на енергийна ефективност в сградата; подобряване на достъпа на лицата с увреждания до и вътре в съответната сградана, както и доставка и монтаж на оборудване |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Savings in annual primary energy consumption, Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 278.86 , Reached amount: 0.00 |
| Indicator 2 | Renovation and/or construction works of schools, kindergartens and student dormitories, and construction works of campuses, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 3 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 350.00 , Reached amount: 0.00 |
| Total Project cost | 1 275 805.31 EUR |
| Grant | 1 275 805.31 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 769 348.96 EUR |
| Percentage of EU co-financing | 83.47 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: "ОБНОВЯВАНЕ НА ИНФРАСТРУКТУРАТА И МЕРКИ ЗА ПОВИШАВАНЕ НА ЕНЕРГИЙ-НАТА ЕФЕКТИВНОСТ, РЕМОНТ И ДОСТАВКА НА ОБОРУДВАНЕ И ОБЗАВЕЖДАНЕ НА СГРАДАТА НА СУ „ХРИСТО СМИРНЕНСКИ“ - ГР. КОЙНАРЕ",
Estimated Amount: 1 035 461.63
|
| Procedure 2 |
Subject to due process: „Извършване на консултантски услуги по чл. 166, ал. 1, т. 1 от Закона за устройство на територията (ЗУТ) в имоти, находящи се в териториалния обхват на Община Червен бряг, област Плевен“ по обособени позиции:,
Estimated Amount: 50 617.90
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN