Identification

UMIS Number BG-RRP-1.015-1264-C02
Project Name Building a school STEM environment in 52. Primary School "Tsanko Tserkovski", Sofia
Beneficiary 000668099 52-RO OSNOVNO UCHILISHTE "TSANKO TSERKOVSKI"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 17.09.2024
Start Date 17.09.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Град (BG411), Столична, гр.София

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM център и ВОСКС в 52. ОСНОВНО УЧИЛИЩЕ "ЦАНКО ЦЕРКОВСКИ", ГР. СОФИЯ: „Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване.“, Contracted Amount: 167 826.52 , Reported Amount: 154 724.67

Participating Organizations

Partners None
Contractors
  • Contractor: KONTRAX AD , Contracted Amount*: 121 860.90 , Reported Amount**: 121 860.90
  • Contractor: "LB EXPERT" Ltd , Contracted Amount*: 32 863.78 , Reported Amount**: 32 863.77
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 84.00 , Reached amount: 0.00

Financial Information

Total Project cost 169 504.78 EUR
Grant 169 504.78 EUR
Self amount 0.00 EUR
Total actual amounts paid 156 014.04 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка на ободрудване , Estimated Amount: 10 091.25
  • Differentiated position 1: Доставка и монтаж/инсталиране на оборудване по направление „Природни науки“
    Contractor: "LB EXPERT" Ltd
    Contract total funded value: 10 091.25
Procedure 2 Subject to due process: ДОСТАВКА, МОНТАЖ И ГАРАНЦИОННО ОБСЛУЖВАНЕ НА ОБОРУДВАНЕ ЗА ИЗГРАЖДАНЕ НА СТЕМ СРЕДА И ВОСКС, Estimated Amount: 101 599.83
  • Differentiated position 1: ДОСТАВКА, МОНТАЖ И ГАРАНЦИОННО ОБСЛУЖВАНЕ НА ОБОРУДВАНЕ ЗА ИЗГРАЖДАНЕ НА СТЕМ СРЕДА И ВОСКС
    Contractor: KONTRAX AD
    Contract total funded value: 121 860.90
Procedure 3 Subject to due process: Изработка, доставка и монтаж на обзавеждане, Estimated Amount: 22 772.53

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN