Identification

UMIS Number BG-RRP-1.015-2015-C01
Project Name Concept for building a school STEM environment at NU Vasil Levski
Beneficiary 000012066 VASIL LEVSKI PRIMARY SCHOOL
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 12.09.2024
Start Date 12.09.2024
End Date 13.03.2026
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), Благоевград (BG413), Сатовча, с.Осина

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM център и ВОСКС в училище: „Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване.“;, Contracted Amount: 30 612.00 , Reported Amount: 58 730.56

Participating Organizations

Partners None
Contractors
  • Contractor: "DECOR M" LTD, Contracted Amount*: 1 015.58 , Reported Amount**: 2 031.16
  • Contractor: IS TEKS LTD, Contracted Amount*: 667.54 , Reported Amount**: 1 335.08
  • Contractor: ROSSTROY - IS Ltd, Contracted Amount*: 143.02 , Reported Amount**: 286.04
  • Contractor: A1 Bulgaria EAD, Contracted Amount*: 27 539.14 , Reported Amount**: 55 078.28
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 13.00 , Reached amount: 13.00

Financial Information

Total Project cost 29 610.00 EUR
Grant 29 610.00 EUR
Self amount 0.00 EUR
Total actual amounts paid 29 609.99 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN