| UMIS Number | BG-RRP-1.011-0033-C01 |
| Project Name | "Reconstruction and basic renovation of the dormitory building at the Professional High School of Agrarian Technologies "Tsanko Tserkovski" Pavlikeni" |
| Beneficiary | 000133901 Pavlikeni municipality |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 17.01.2024 |
| Start Date | 17.01.2024 |
| End Date | 31.05.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Настоящото проектно предложение е насочено към решаване на проблема с остарялата материална база на общежитието към ПГАТ "Цанко Церковски" гр.Павликени и привеждането и в съответствие със съвременните изисквания за такъв тип сгради. След извършване на интервенцията ще се осигурят качествени и модерни условия за живот и самоподготовка на учениците на ПГАТ "Цанко Церковски" гр.Павликени, които са настанени в общежитието.Предвидени за изпълнение са следните дейности: 1.Изпълнение на строително-монтажни работи, осъществяване на строителен и авторски надзор, инвеститорски контрол и въвеждане на обекта в експлоатация; 2.Доставка и монтаж на обзавеждане и оборудване. В резултата на изпълнението на проекта, ПГАТ "Цанко Церковски" гр.Павликени ще повиши своята конкурентноспособност за привличане на ученици и повиши качеството но образователния процес. Въвеждането на мерките за енергийна ефективност ще намали разходите за осветление и отопление, а спестените средства ще се инвестират за повишаване качеството на образованието. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Finalisation of renovation activities in student dormitories, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Savings in annual primary energy consumption, Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 70.49 , Reached amount: 0.00 |
| Indicator 3 | Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 174.00 , Reached amount: 0.00 |
| Total Project cost | 3 067 480.44 EUR |
| Grant | 3 067 480.44 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 1 423 339.88 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: "Осъществяване на независим строителен надзор и инвеститорски контрол по време на строителството за обект „Реконструкция и основно обновяване на сградата на общежитието към ПГАТ „Цанко Церковски” гр. Павликени“,
Estimated Amount: 27 000.00
|
| Procedure 2 |
Subject to due process: „Доставка и монтаж на оборудване и обзавеждане на обект „Реконструкция и основно обновяване на сградата на общежитието към ПГАТ „Цанко Церковски”, гр. Павликени”,
Estimated Amount: 126 065.83
|
| Procedure 3 |
Subject to due process: „РЕКОНСТРУКЦИЯ И ОСНОВНО ОБНОВЯВАНЕ НА СГРАДАТА НА ОБЩЕЖИТИЕТО КЪМ ПГАТ „ЦАНКО ЦЕРКОВСКИ“, ГР. ПАВЛИКЕНИ“, С АДМИНИСТРАТИВЕН АДРЕС ГР. ПАВЛИКЕНИ, БУЛ. „РУСКИ“ № 46“,
Estimated Amount: 4 632 495.21
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN