Identification

UMIS Number BG-RRP-1.015-2234-C01
Project Name Building school STEM environment and high-tech equipped and connected classrooms.
Beneficiary 000185289 PROFESSIONAL HIGH SCHOOL OF MECHANICAL AND ELECTRICAL ENGINEERING "CHRISTO SMIRNENSKI"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 24.10.2024
Start Date 24.10.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Плевен (BG314), Кнежа, гр.Кнежа

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).: „Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване.“;, Contracted Amount: 120 991.28 , Reported Amount: 110 628.46

Participating Organizations

Partners None
Contractors
  • Contractor: VITA TRADE 77, Contracted Amount*: 49 999.97 , Reported Amount**: 25 564.57
  • Contractor: PANDA Cooperative, Contracted Amount*: 183 214.20 , Reported Amount**: 85 063.89
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 60.00 , Reached amount: 0.00

Financial Information

Total Project cost 122 201.20 EUR
Grant 122 201.20 EUR
Self amount 0.00 EUR
Total actual amounts paid 96 545.64 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: „ДОСТАВКА И МОНТАЖ НА ОБОРУДВАНЕ ЗА ИЗГРАЖДАНЕ НА STEM СРЕДА ЗА НУЖДИТЕ НА ПГМЕТ „ХРИСТО СМИРНЕНСКИ“, ГР. КНЕЖА“, ПО ОБОСОБЕНИ ПОЗИЦИИ", Estimated Amount: 130 660.29
  • Differentiated position 1: ОБРАЗОВАТЕЛНО ОБОРУДВАНЕ
    Contractor: PANDA Cooperative
    Contract total funded value: 108 162.25
  • Differentiated position 2: ВИСОКОТЕХНОЛОГИЧНО ОБОРУДВАНЕ
    Contractor: PANDA Cooperative
    Contract total funded value: 45 947.82

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN