| UMIS Number | BG-RRP-11.010-0066-C02 |
| Project Name | arrying out construction activities, reconstruction of a building and delivery of equipment and furniture with a view to reforming a Home for the elderly in the village of Kovachevtsi |
| Beneficiary | 000776491 Municipality of Samokov |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 22.11.2024 |
| Start Date | 22.11.2024 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Изпълнението на проекта дава възможност за извършване на строителни дейности и доставка на оборудване с оглед реформиране на съществуващи дом за стари хора в съответствие със стандартите за качество на резидентната грижа за възрастни хора в надтрудоспособна възраст. Реформирания дом ще бъде достъпен за всички хора в надтрудоспособна възраст, в който ще се предоставят дейности за подкрепа, превенция за преодоляване на социалното изключване, реализиране на права и подобряване качеството на живот. . |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Savings in annual primary energy consumption, Measure Unit: MWh/y, Base Value: 0.00 , Target amount: 179.00 , Reached amount: 0.00 |
| Indicator 2 | Long-term care establishments and homes for old people renovated and/or constructed, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 1 068 807.16 EUR |
| Grant | 1 068 807.16 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 621 610.01 EUR |
| Percentage of EU co-financing | 85.13 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: "Извършване на строителни дейности, преустройство на сграда с оглед реформиране на дом за стари хора с. Ковачвци",
Estimated Amount: 777 931.44
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN