Identification

UMIS Number BG-RRP-6.004-3129-C05
Project Name Modernization of agriculture through investment in innovation and environmental protection
Beneficiary 179453319 ZP Tsvetan Hristov Ivanov
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 19.06.2024
Start Date 19.06.2024
End Date 30.04.2026
Status of Implementation of the Contract/Order of the Grant Contracted
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Област (BG412), Костинброд, гр.Костинброд

Description

Brief description
Настоящият проект ще бъде реализиран от ЗП Цветан Христов Иванов – земеделски производител, регистриран в Общинска служба „Земеделие” – гр. Костинброд , обл. София. Кандидатът развива основната си дейност в областта на животновъдството – кокошки - носачки. За целта на проекта, ЗП Цветан Христов Иванов е насочил инвестицията към закупуване на специализирано мобилно и автоматизирано оборудване, необходимо за модернизиране и надграждане на животновъдната ферма, без да се променя капацитета на обекта, както и подобряване функицониране на конкурентоспособно животновъдно стопанство и повишаване на биосигурността в животновъдният обект, чрез инвестиции в иновации, консервацинно земеделие – иновации и дейности свързани опазване на околната среда.
Activities
  • Activity: Закупуване на Автоматизирана мобилна ферма за кокошки носачки : Ще бъде закупена Автоматизирана мобилна ферма за кокошки носачки , Contracted Amount: 268 274.85 , Reported Amount: 0.00

Participating Organizations

Partners
  • Partner: ZP, Contracted Amount*: 0.00 , Reported Amount: 0.00
Contractors None
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Award of grant agreements for support under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00
Indicator 2 Projects under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 268 274.85 EUR
Grant 134 137.43 EUR
Self amount 134 137.42 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN