Identification

UMIS Number BG-RRP-4.032-0050-C01
Project Name Installation of a battery energy storage system (BESS) with an installed power of 200 kW to an existing 450 kW Photovoltaic power plant, that was put into operation in 2023.
Beneficiary 201628907 EKO INTER ENERDGY Ltd
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 08.03.2025
Start Date 08.03.2025
End Date 31.03.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пловдив (BG421), Карлово, гр.Клисура

Description

Brief description
Предложението е изграждане на локално съоръжение за съхранение на ел.енергия с инсталирана мощност от 200kW, с капацитет на съхранение от 430 до 480kWh към съществуваща ФЕЦ 450 kW. Централата  въведена в експлоатация през 2023г., и се намира в землището на гр.Клисура, общ. Карлово, обл. Пловдив.
Activities
  • Activity: Разработка на работни проекти: разработване на проектите от лицензиран проектант, Contracted Amount: 306.78 , Reported Amount: 306.78
  • Activity: Избор на доставчик на ЛСС и поръчка на продукта: Проучване на различни оферти от производители и търговци и избор на най-подходящия продукт съотношение цена/качество. Време за доставка и транспорт на продукта, което може да отнеме 2-3 месеца., Contracted Amount: 59 309.86 , Reported Amount: 65 369.81
  • Activity: Доставка и монтаж на ЛСС: Системата за съхранение ще бъде доставена и монтирана. Ще бъдат извършени и настройки за управелние на системата., Contracted Amount: 511.28 , Reported Amount: 1 511.29
  • Activity: Пускане в експлоатация на системата за съхранение.: След приключване на всички дейности ще въведем съоръжението в експлоатация и ще предоставим план за експлоатация и управление на ЛСС, според изискванията за програмата. Ще сключим необходимите застраховки и банкова гаранция., Contracted Amount: 102.26 , Reported Amount: 332.48
  • Activity: Получаване на разрешение за поставяне (строеж) на ЛСС: Получаване на разрешение за поставяне (строеж) на ЛСС, Contracted Amount: 0.00 , Reported Amount: 0.00

Participating Organizations

Partners None
Contractors
  • Contractor: G M TRANS LOGISTIC Ltd, Contracted Amount*: 332.34 , Reported Amount**: 0.00
  • Contractor: Tianjin Pulan Energy Technology Co ltd, Contracted Amount*: 23 500.11 , Reported Amount**: 0.00
  • Contractor: World Transport Overseas Ltd, Contracted Amount*: 3 710.00 , Reported Amount**: 0.00
  • Contractor: V - RENESANS LTD, Contracted Amount*: 153.39 , Reported Amount**: 0.00
  • Contractor: SUNSERVICE Ltd, Contracted Amount*: 255.65 , Reported Amount**: 0.00
  • Contractor: Bulmedin EOOD, Contracted Amount*: 1 585.01 , Reported Amount**: 0.00
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.20 , Target amount: 0.20 , Reached amount: 0.00
Indicator 2 Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.43 , Target amount: 0.48 , Reached amount: 0.00
Indicator 3 Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.45 , Target amount: 0.45 , Reached amount: 0.00

Financial Information

Total Project cost 60 230.18 EUR
Grant 30 115.09 EUR
Self amount 30 115.09 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: ПРОУЧВАНЕ И ИЗБОР НА ИЗПЪЛНИТЕЛ за Tехнически ръководител за проект насочен към изграждане на система за съхранение на ел. енергия, Estimated Amount: 511.28
  • Differentiated position 1: Tехнически ръководител за проект насочен към изграждане на система за съхранение
    Contractor: SUNSERVICE Ltd
    Contract total funded value: 255.65
Procedure 2 Subject to due process: ПРОУЧВАНЕ И ИЗБОР НА ИЗПЪЛНИТЕЛ за доставка на Локална система за съхранение на електрическа енергия (ЛСС) за програмата , Estimated Amount: 51 129.19
  • Differentiated position 1: Tianjin Pulan Energy Technology Co., Ltd.
    Contractor: Tianjin Pulan Energy Technology Co ltd
    Contract total funded value: 23 500.11
Procedure 3 Subject to due process: ПРОУЧВАНЕ И ИЗБОР НА ИЗПЪЛНИТЕЛ за Изготвяне на инвестиционен проект за изграждане на „Локални съоръжения за съхранение на електрическа енергия с мощност 0,2 МW и капацитет 0.43-0.48 МWh към ФЕЦ, м-ст „Каменидица“, гр. Клисура, общ. Карлово обл. Пловдив, Estimated Amount: 306.78
  • Differentiated position 1: Договор за за Изготвяне на инвестиционен проект за изграждане на „Локални съоръжения за съхранение на електрическа енергия
    Contractor: V - RENESANS LTD
    Contract total funded value: 153.39
Procedure 4 Subject to due process: ПРОУЧВАНЕ И ИЗБОР НА ИЗПЪЛНИТЕЛ за корабен транспорт по маршрут Шанхай , Китай - пристанище Варна, Estimated Amount: 7 420.00
  • Differentiated position 1: Корабен транспорт по маршрут Шанхай , Китай - пристанище Варна
    Contractor: World Transport Overseas Ltd
    Contract total funded value: 3 710.00
Procedure 5 Subject to due process: ПРОУЧВАНЕ И ИЗБОР НА ИЗПЪЛНИТЕЛ за привеждане на 2 бр. системи за съхранение на енергия (BESS), в съответствие с актуалните технически изисквания на „ЕР Юг" ЕАД, кабелно свързване на двете системи за съхранение към съществуващия Бетонен комплектен трансформаторен пост (БКТП)., Estimated Amount: 3 817.00
  • Differentiated position 1: Договор Булмедин
    Contractor: Bulmedin EOOD
    Contract total funded value: 1 585.01
Procedure 6 Subject to due process: ПРОУЧВАНЕ И ИЗБОР НА ИЗПЪЛНИТЕЛ за Транспорт на Системи за съхранение на електрическа енергия и батерийни пакети към тях по маршрут с.Тополи, Варна до гр.Клисура,общ. Карлово, обл. Пловдив., Estimated Amount: 664.68
  • Differentiated position 1: ДОГОВОР ЗА Транспорт на Системи за съхранение на електрическа енергия и батерийни пакети към тях по маршрут с.Тополи, Варна до гр.Клисура,общ. Карлово, обл. Пловдив
    Contractor: G M TRANS LOGISTIC Ltd
    Contract total funded value: 332.34

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN