| UMIS Number | BG-RRP-3.004-2118-C01 |
| Project Name | Technological Modernization of the Enreprise |
| Beneficiary | 111005252 BALKAN JSC |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 10.04.2023 |
| Start Date | 10.04.2023 |
| End Date | 03.07.2024 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
Основната цел на настоящото проектно предложение е да допринесе за повишаване на ефективността на производствените процеси, да се постигне по-висока производителност, да се намалят производствените разходи и да се оптимизира производствената верига чрез цифровизация и разширяване на производствения капацитет на предприятието с въвеждане на ново високотехнологично оборудване, специализирано в производството на метални елементи. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Bugdet execution – transfer of at least EUR 120 million for technological modernisation, Measure Unit: млн. евро, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Indicator 2 | Enterprises supported (of which small – including micro, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Total Project cost | 715 808.64 EUR |
| Grant | 357 904.32 EUR |
| Self amount | 357 904.32 EUR |
| Total actual amounts paid | 357 904.32 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка, монтаж и въвеждане в експлоатация на Машина за лазерно рязане - 1 бр.,
Estimated Amount: 536 856.48
|
| Procedure 2 |
Subject to due process: Доставка, монтаж и въвеждане в експлоатация на Машина за многоточково електросъпротивително заваряване - 1 бр.,
Estimated Amount: 178 952.16
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN