| UMIS Number | BG-RRP-4.020-0007-C02 |
| Project Name | Implementation of Energy Efficiency Measures in the Administrative Complex of the Municipal Administration - Pordim, town of Pordim, Pordim Municipality, Pleven District |
| Beneficiary | 000413999 OBSHTINA PORDIM |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 24.04.2024 |
| Start Date | 24.04.2024 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Един от основните проблеми в общ. Пордим е ниското равнище на енергийната ефективност и фактът, че все още няма газифицирани населени места в общината. Обществените и частни сгради се отопляват предимно на твърдо гориво и електрическа енергия. Външните стени на сградата, обект на интервенция по проекта имат до 5 пъти по-големи топлинни загуби в сравнение с нормите за ново строителство. Базисно проектът е насочен към подобряване качеството на достъпа да обществени услуги на населението, живеещо в Общ. Пордим. Настоящият проект е фокусиран върху подобряване на сградния фонд в Общ. Пордим чрез ремонт на обществена сграда. С изпълнението на мерки в тази целева посока, проектът ще допринесе за изграждане на добра градска инфраструктура; приспособяване на сградата за лица с увреждания; облагородяване на публичните сгради, като по този начин създава условия за по-добър начин на живот в по-привлекателна градска среда. Обект на проекта е една сграда (Административна сграда на Община Пордим), която съставлява административния комплекс на Общ. Пордим. В сградата ще бъдат въведени мерки за повишаване на енергийната ефективност, в това число и използването на ВЕИ за собствени нужди. Целите на проекта са: 1. Въвеждане на мерки за енергийна ефективност. Понижаване на разходите за отопление и охлаждане, както и намаляване на вредните емисии във въздуха. 2. Постигане на здравословна, безопасна и естетическа среда за административно обслужване. 3. Създаване на равни условия за развитие на лицата в неравностойно положение чрез въвеждане на мерки за общодостъпна среда. Освен извършването на СМР, проектът предвижда: Изпълнение на авторски и строителен надзор, мерки за информация и публичност и управление на проекта. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Намаляване на емисиите на парникови газове, Measure Unit: тонове CO2 екв., Base Value: 0.00 , Target amount: 23.78 , Reached amount: 0.00 |
| Indicator 2 | Completed energy-efficiency renovation of non- residential buildings – renovated surface of public buildings (sub-measure 2), Measure Unit: m2, Base Value: 0.00 , Target amount: 1 368.96 , Reached amount: 0.00 |
| Indicator 3 | Reduction of annual primary energy consumption, Measure Unit: kWh/година, Base Value: 0.00 , Target amount: 101 462.90 , Reached amount: 0.00 |
| Indicator 4 | Energy efficiency renovation of non-residential buildings, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 260 515.03 EUR |
| Grant | 255 893.09 EUR |
| Self amount | 4 621.94 EUR |
| Total actual amounts paid | 255 872.09 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Наименование: "Избор на изпълнител за осъществяване на задължителен авторски надзор, съгласно ЗУТ". Предметът на поръчката обхваща упражняване на авторски надзор при изпълнение на строително-монтажни работи в Община Пордим за обект: Административна сграда на Община Пордим с административен адрес ул. "Иван Божинов" № 1.,
Estimated Amount: 4 400.00
|
| Procedure 2 |
Subject to due process: Наименование: "Избор на изпълнител за осъществяване на задължителен строителен надзор, съгласно ЗУТ". Предметът на поръчката обхваща упражняване на строителен надзор при изпълнение на строително-монтажни работи в Община Пордим за обект: Административна сграда на Община Пордим с административен адрес ул. "Иван Божинов" № 1.,
Estimated Amount: 8 880.00
|
| Procedure 3 |
Subject to due process: Наименование: "Избор на изпълнител за управление на проект - Въвеждане на мерки за енергийна ефективност в административния комплекс на Общинска администрация - Пордим, гр. Пордим, община Пордим, област Плевен, в това число изпълнение на мерки за информация и публичност по проекта. Предметът на поръчката обхваща предоставянето на консултантски услуги (административни, финансови и юридическо-правни) на Община Пордим за управление на гореспоменатия проект.,
Estimated Amount: 9 120.00
|
| Procedure 4 |
Subject to due process: Наименование: "Извършване на СМР и въвеждане на ЕСМ в Административна сграда на Община Пордим с административен адрес ул. "Иван Божинов" № 1. Предметът на поръчката обхваща извършване на СМР, включително изграждане на ВЕИ инсталация за производство на ел. енергия за собствени нужди.,
Estimated Amount: 467 079.12
|
| Procedure 5 |
Subject to due process: Наименование: Последващ енергиен одит за потвърждение на постигнати енергийни спестявания за обект: Административна сграда на Община Пордим с административен адрес ул. "Иван Божинов" № 1.,
Estimated Amount: 2 431.67
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN