| UMIS Number | BG-RRP-4.023-1419-C02 |
| Project Name | Implementation of measures for increasing the energy efficiency of a multi-family residential building with address "Stefan Stambolov" street No. 27, town of Haskovo. |
| Beneficiary | 000903946 OBSHTINA HASKOVO |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 05.12.2024 |
| Start Date | 05.12.2024 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проект "Въвеждане на мерки за повишаване на енергийната ефективност на многофамилна жилищна сграда с адрес гр. Хасково, ул. "Стефан Стамболов" №27" е насочен към изпълнение на местните политики за прилагане на устойчив модел на управление на сградния жилищен фонд на територията на град Хасково. Проектът е в съответствие с основната цел на процедура BG-RRP-4.023 по НПВУ и ще бъде реализиран чрез изпълнение на комплекс от мерки за енергийна ефективност. Сградата, обект на интервенция е частна собственост и за целта е сключено Споразумение за партньорство между Община Хасково и Сдружението на собствениците (краен получател) /регистрирани по реда на чл. 25, ал. 1 от ЗУЕС/. Проектът предвижда изпълнение на дейности за проектиране и извършване на СМР, включващи мерки за енергийна ефективност, предписани като задължителни за сградата в обследването за енергийна ефективност; съпътстващи строителни и монтажни работи, свързани с изпълнението на мерките за енергийна ефективност и съответното възстановяване на общите части на сградата в резултат на изпълнените мерки с енергоспестяващ ефект; СМР, които произтичат от нормативни изисквания, свързани с безопасната експлоатация на сградите и са предписани като задължителни в техническия паспорт на сградата, изграждане на достъпна среда и СМР, които са нормативно необходими за въвеждане на сградата в експлоатация. След изпълнение на предвидените мерките в многофамилната сграда ще се постигне клас на енергопотребление "А". ПИИ включва и дейности за осигуряване на качествено управление и организация на проекта, вкл. дейности за информация и комуникация. Предвидените дейности са съобразени с принципа за „ненанасяне на значителни вреди“, по смисъла на чл. 17 от Регламента за таксономията. При реализирането на настоящото ПИИ ще бъдат съблюдавани хоризонталните политики на Европейския съюз. |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors |
|
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Energy-efficiency renovation of residential buildings, Measure Unit: Renovated gross floor area of residential buildings (m2), Base Value: 0.00 , Target amount: 6 035.00 , Reached amount: 0.00 |
| Indicator 2 | Reduced greenhouse emissions, Measure Unit: Tones CO2, Base Value: 0.00 , Target amount: 165.72 , Reached amount: 0.00 |
| Indicator 3 | Reduction of the annual consumption of primary energy kWh/year., Measure Unit: kWh/година, Base Value: 1 115 912.51 , Target amount: 331 389.63 , Reached amount: 0.00 |
| Indicator 4 | % in primary non-renewable energy consumption, Measure Unit: %, Base Value: 0.00 , Target amount: 70.30 , Reached amount: 0.00 |
| Indicator 5 | Number of renovated housing units, Measure Unit: Number, Base Value: 0.00 , Target amount: 60.00 , Reached amount: 0.00 |
| Total Project cost | 646 071.33 EUR |
| Grant | 646 040.65 EUR |
| Self amount | 30.68 EUR |
| Total actual amounts paid | 399 289.01 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: „Дейности по осъществяване на мерки за комуникация, информация и публичност, по ПИИ на община Хасково, финансирани от Националния план за възстановяване и устойчивост по обособени позиции. За Обособена позиция 2 - "Комуникация, информация и публичност на проекти, финансиран по процедура BG-RRP-4.023 - „Подкрепа за устойчиво енергийно обновяване на жилищния сграден фонд -Етап I“ и процедура BG-RRP-4.020 - „Подкрепа за устойчиво енергийно обновяване на публичен сграден фонд за административно обслужване, култура и спорт“, Компонент 4 „Нисковъглеродна икономика“,
Estimated Amount: 2 300.81
|
| Procedure 2 |
Subject to due process: „Избор на изпълнител за изготвяне на независима експертна оценка от сертифициран енергиен одитор, след приключване на дейностите по изпълнение на СМР на следния обект:
Обект №1„ Въвеждане на мерки за енергийна ефективност на сграда с административен адрес гр. Хасково, ул. ”Стефан Стамболов” № 27“,
Estimated Amount: 3 702.78
|
| Procedure 3 |
Subject to due process: Избор на изпълнител за изготвяне на оценки на съответствие на инвестиционни проекти и упражняване на строителен надзор на многофамилни жилищни сгради в град Хасково, за които ще се въвеждат мерки за енергийна ефективност, по единадесет обособени позиции.
За Обособена позиция №8 „Сграда с административен адрес: гр. Хасково, ул. "Стефан Стамболов" №27",
Estimated Amount: 15 921.94
|
| Procedure 4 |
Subject to due process: Изпълнение на Инжинеринг (проектиране,СМР и авторски надзор) за въвеждане на мерки за енергийната ефективност на многофамилна жилищна сгради в град Хасково по единадесет обособени позиции. За Обособена позиция №8, „Сграда с административен адрес: гр. Хасково, ул. "Стефан Стамболов" №27"
,
Estimated Amount: 606 317.19
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN