| UMIS Number | BG-RRP-4.032-0225-C01 |
| Project Name | Delivery and installation of a 400 KW Battery Energy Storage System (SES) to an 800 KW Photovoltaic Power Plant |
| Beneficiary | 205458007 "SOLAR - PAZARDJIK"LTD |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 10.11.2025 |
| Start Date | 10.11.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектното предложение предвижда изграждане на фотоволтаична електрическа централа с мощност от 800 КW и локално съоръжение за съхранение на енергия чрез батерии с мощност от 400 KW. Дейностите по проекта ще се осъществят на територията на община Пазарджик, в рамките на имот с идентификатор 00254.95.9, УПИ II-9, в землището на с. Алеко Константиново, местност "Гьола", ЕКАТТЕ 00254. Производителността на фотоволтаичните системи, която е най-висока в часовете с най-силно слънцегреене, не винаги съвпада с часовете на пикова консумация в енергийната система. В този аспект акумулаторните батерии са решение, което предоставя възможност генерираната през деня енергия да се потребява в часовете с пиково потребление. По този начин се оптимизира използването на генерираната през светлата част от деня енергия до изчерпване на натрупания в батериите запас. |
| Activities |
|
| Partners | None |
| Contractors | None |
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.40 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 0.83 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 0.80 , Reached amount: 0.00 |
| Total Project cost | 382 957.62 EUR |
| Grant | 191 478.81 EUR |
| Self amount | 191 478.81 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| There are no tender procedures |
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN