Identification

UMIS Number BG-RRP-6.004-0784-C03
Project Name Technological and ecological modernization of the agricultural holding
Beneficiary TZVETOMIR
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 10.12.2025
Start Date 10.12.2025
End Date 30.04.2026
Status of Implementation of the Contract/Order of the Grant Contracted
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Плевен (BG314), Долна Митрополия, с.Славовица

Description

Brief description
Инвестиционният проект предвижда модернизиране на земеделското стопанство, чрез въвеждане на иновативни технологии и закупуване на трактор с високо ниво на технологични решения
Activities
  • Activity: Технологична и екологична модернизация на земеделското стопанство : Закупуване на трактор с високо ниво на технологични решения на стойност 697 840,14 лева без ДДС, Contracted Amount: 356 800.00 , Reported Amount: 0.00

Participating Organizations

Partners
  • Partner: TZVETOMIR NIKOLAEV VASILEV, Contracted Amount*: 0.00 , Reported Amount: 0.00
Contractors
  • Contractor: AGROLA, Contracted Amount*: 356 800.00 , Reported Amount**: 0.00
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Award of grant agreements for support under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00
Indicator 2 Projects under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00

Financial Information

Total Project cost 356 800.00 EUR
Grant 178 400.00 EUR
Self amount 178 400.00 EUR
Total actual amounts paid 0.00 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN