| UMIS Number | BG-RRP-4.032-0048-C01 |
| Project Name | LOCAL ENERGY STORAGE FACILITIES wich an installed power of 400kW(BATTERY FARM) combined with a PHOTOVOLTAIC INSTALLATION for the production of electricity from RES with an installed power of 900 kW for own use and saling of the surplus |
| Beneficiary | 121353182 DOMOSTROITELEN COMBINAT- SOFIA |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 17.02.2025 |
| Start Date | 17.02.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Изграждане на ЛСС с инсталирана мощност от 400кW, като част от изградена, но все още невъведена в есплоатация Фотоволтаична Система за производство на електроенергия с инсталирана мощност 900кW. Батерийното стопанство ще се състои от 4бр.устройства, всяко от които с мощност от 100кW, като всяко устройство представлява съвкупност от акумулаторни батерии и хибриден инвертор с интелигентно управление, който управлява циклите и нивата на зареждане и разреждане на акумулаторните батерии. Батерийното стопанство се инсталира и се свързва към електрическата система на обекта заедно с фотоволтаичната инсталация по приложена еднолинейна електрическа схема. АДРЕС: Сграда с идентификатор 68134.200.70.1, находяща се в ПИ 68134.200.70, УПИ V-376, кв. 36, обл. София, гр. София, общ. Столична, р-н Красно село, ул. Костенец №12 |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.40 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 0.86 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 0.90 , Reached amount: 0.00 |
| Total Project cost | 226 706.84 EUR |
| Grant | 113 353.42 EUR |
| Self amount | 113 353.42 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка на Локално съоръжение за съхранение на електроенергия с инсталирана мощност 400 kW (батерийно стопанство), включваща 4 броя батерии с капацитет по 215kWh всяка, 4 броя инвертори с управление по 100kW всеки - Напрежение 3x400/230V, 50Hz, конвертори, охлаждаща система. Доставка на ново поле-6 (електрическо табло) - по приложена еднолинейна електрическа схема и Система за мониторинг и управление. Извършване на строително-монтажни работи по изграждането на ЛСС , включително монтажа и инсталирането на мониторингови системи за контрол и връзката с фотоволтаичната електроцентрала и електрическата мрежа,
Estimated Amount: 224 508.27
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN