Identification

UMIS Number BG-RRP-1.015-0129-C01
Project Name Building school STEM environment and HECC in Sports school 'Todor Kableshkov' - Stara Zagora city.
Beneficiary 000806785 SPORTNO UCHILISHTE "TODOR KABLESHKOV"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 18.03.2024
Start Date 18.03.2024
End Date 08.04.2026
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Стара Загора (BG344), Стара Загора, гр.Стара Загора

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищна STEM среда и ВОСКС в СПОРТНО УЧИЛИЩЕ "ТОДОР КАБЛЕШКОВ" - гр. Стара Загора: Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване., Contracted Amount: 126 798.89 , Reported Amount: 253 433.27

Participating Organizations

Partners None
Contractors
  • Contractor: YUNION INTERAKTIV OOD, Contracted Amount*: 91 979.45 , Reported Amount**: 183 867.47
  • Contractor: „Era Build 2020“ Ltd, Contracted Amount*: 34 782.90 , Reported Amount**: 69 565.80
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 110.00 , Reached amount: 110.00

Financial Information

Total Project cost 127 772.61 EUR
Grant 127 772.61 EUR
Self amount 0.00 EUR
Total actual amounts paid 127 772.61 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: „ДОСТАВКА, МОНТАЖ И ВЪВЕЖДАНЕ В ЕКСПЛОАТАЦИЯ НА ТЕХНОЛОГИЧНО ОБОРУДВАНЕ ЗА ИЗГРАЖДАНЕ STEM ЦЕНТЪР В СПОРТНО УЧИЛИЩЕ „ТОДОР КАБЛЕШКОВ“, ГР. СТАРА ЗАГОРА“, Estimated Amount: 67 672.66
  • Differentiated position 1: Договор с изпълнител
    Contractor: YUNION INTERAKTIV OOD
    Contract total funded value: 81 053.06

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN