| UMIS Number | BG-RRP-13.009-0028-C01 |
| Project Name | "Installation of a photovoltaic system in an existing social services building located in UPI I-483-kindergarten and social services in district 43 of the PUP of the village of Lesichovo and purchase of an electric vehicle, including a connected charging station for the provision of social services." |
| Beneficiary | 000351693 Municipality of Lesichovo |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 18.11.2025 |
| Start Date | 18.11.2025 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектното предложение на община Лесичово е за инсталиране на фотоволтаична система в съществуваща сграда за предоставяне на социални услуги, делегирани от държавата дейности. Произведената електроенергия е предназначена изцяло за собствено потребление за нуждите на следните социални услуги: - Център за настаняване от семеен тип за деца без увреждания 1 - капацитет 15 деца; - Център за настаняване от семеен тип за деца без увреждания 2 - капацитет 10 деца; - Център за обществена подкрепа - капацитет 15 деца и лица. Предвижда се и закупуване на съоръжение за съхранение на електрическа енергия (батерия). Проектното предложение предвижда също и закупуване на електрическо превозно средство и свързана зарядна станция за целите на предоставяне на социалните услуги в община Лесичово. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Purchased electric vehicles and connected charging stations, each with a minimum power of 22 kW, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Number of social services with installed PV power plants with a capacity of 15 to 30 kW, Measure Unit: Number, Base Value: 0.00 , Target amount: 3.00 , Reached amount: 0.00 |
| Total Project cost | 158 829.25 EUR |
| Grant | 158 829.25 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 156 414.46 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: „Закупуване на електрически автомобил“,
Estimated Amount: 46 670.86
|
| Procedure 2 |
Subject to due process: СМР на обект: „Инсталиране на ФЕЦ с мощност 60 kW на покривна конструкция на съществуваща сграда за социални услуги в УПИ I-483- За детска градина и социални услуги, кв. 43 по плана на с.Лесичово”,
Estimated Amount: 81 910.24
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN