Identification

UMIS Number BG-RRP-1.015-0140-C02
Project Name Building a school STEM environment in "Hristo Botev" Elementary School
Beneficiary 000581648 NU "HRISTO BOTEV"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 15.03.2024
Start Date 15.03.2024
End Date 20.10.2025
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Сливен (BG342), Твърдица, с.Оризари

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС): Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда /Приложение №2 към Поканата/, подписана с електронен подпис от директора на училището /или оправомощено от него лице/ и от директора на националния STEM център/или от оправомощено от него лице/ и прикачено в секция 12 от Формуляра за кандидатстване., Contracted Amount: 30 970.46 , Reported Amount: 61 838.72

Participating Organizations

Partners None
Contractors
  • Contractor: A1 Bulgaria EAD, Contracted Amount*: 25 407.85 , Reported Amount**: 45 017.06
  • Contractor: MG - A STROI LTD, Contracted Amount*: 5 266.41 , Reported Amount**: 10 532.82
  • Contractor: KAN-UCHTEHSPORT-BALGARIA, Contracted Amount*: 2 888.88 , Reported Amount**: 5 777.76
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 12.00 , Reached amount: 12.00

Financial Information

Total Project cost 30 919.36 EUR
Grant 30 919.36 EUR
Self amount 0.00 EUR
Total actual amounts paid 30 919.35 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN