| UMIS Number | BG-RRP-6.004-3225-C03 |
| Project Name | "Investments in digitized agricultural machinery for growing vegetables and construction of a photovoltaic plant for the own needs of Farmer "VALENTIN STOYANOV STOYANOV"" |
| Beneficiary | Farmer |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 14.06.2024 |
| Start Date | 14.06.2024 |
| End Date | 14.06.2025 |
| Status of Implementation of the Contract/Order of the Grant | Contracted |
| Location of Performance |
|
| Brief description |
ЗП "ВАЛЕНТИН СТОЯНОВ СТОЯНОВ" се стреми да бъде напълно конкурентен по отношение на качеството и себестойността на единица продукт спрямо основните зеленчуко производители на такъв вид суровини в региона и в страната. Стратегията за развитие е производство на качествена продукция. Закупуването на предвидените по проеткта активи, като: Навигационна система за контрол на селскостопански машини и обмен на данни между тракторът и прикачният инвента, трактор с челен товарач, пръскачка и фреза са технологични решения, които осигуряват възможност за проследимост и контрол на операциите, управление на процесите и генериране и обмен на данни. Реализирането на проекта ще доведе до цялостно подобряване на иновативни производствени технологии и автоматизиране на работните процеси, с което се подобри качеството на отглежданите зеленчуци и плодове, и ще се намали себестойността им, а от там че се подобри финансовото състояние на кандидата и ще се постигне значителен ръст във всички икономически параметри. |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Award of grant agreements for support under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00 |
| Indicator 2 | Installed additional operational renewable energy capacity in MW, Measure Unit: MW, Base Value: 0.00 , Target amount: 30.00 , Reached amount: 0.03 |
| Indicator 3 | Projects under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Total Project cost | 174 246.22 EUR |
| Grant | 87 123.11 EUR |
| Self amount | 87 123.11 EUR |
| Total actual amounts paid | 87 123.11 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| There are no tender procedures |
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN