| UMIS Number | BG-RRP-4.023-2763-C02 |
| Project Name | Energy efficiency improvement in a residential building located at Sofia city, Sredec district, 91 "Vasil Levski" blvd. and 52 "Aksakov"str. |
| Beneficiary | 0006963270461 Sofia Municipality, DISTRICT "SREDEC" |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 15.01.2025 |
| Start Date | 15.01.2025 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Настоящето проектно предложение е насочено към повишаване на енергийната ефективност в многофамилна жилищна сграда на адрес гр. София, район "Средец", бул. "Васил Левски"№91 и ул. "Аксаков" №52. Предвижда се да се внедрят всички задължителни мерки от енергийното обследване на сградата с цел постигане на енергиен клас А. Сградата е построена през 1931 г. и се намира на административен адрес: гр. София, район "Средец", бул. "Васил Левски"№91 и ул. "Аксаков" №52, УПИ IX, Местност по регулация "Главен градски център ЗОНА Г-8 и ЗОНА Г - 10", Регулационен квартал: 454, КИ 68134.100.190.1. Състои се от 23 обекта, разположени на 6 надземни етажа за високо тяло и 5 надземни етажа за ниско тяло, с обща разгъната площ от 2774,8 кв. м. Наличието на стопански обекти обуславя включването на компоненти в режим на "минимална помощ" в проекта. Изпълнението на проекта в многофамилната жилищната сграда ще включва: I. Топлинно изолиране на външни стени II. Подмяна на съществуваща стара дограма III. Топлинно изолиране на покрив IV. Топлинно изолиране на под |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Energy-efficiency renovation of residential buildings, Measure Unit: Renovated gross floor area of residential buildings (m2), Base Value: 0.00 , Target amount: 2 774.80 , Reached amount: 0.00 |
| Indicator 2 | Reduced greenhouse emissions, Measure Unit: Tones CO2, Base Value: 0.00 , Target amount: 88.08 , Reached amount: 0.00 |
| Indicator 3 | Reduction of the annual consumption of primary energy kWh/year., Measure Unit: kWh/година, Base Value: 611 059.15 , Target amount: 206 857.64 , Reached amount: 0.00 |
| Indicator 4 | % in primary non-renewable energy consumption, Measure Unit: %, Base Value: 0.00 , Target amount: 66.10 , Reached amount: 0.00 |
| Indicator 5 | Number of renovated housing units, Measure Unit: Number, Base Value: 0.00 , Target amount: 22.00 , Reached amount: 0.00 |
| Total Project cost | 341 328.47 EUR |
| Grant | 341 328.47 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 80 370.28 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Изготвяне на комплексен доклад за оценка на съответствие на инвестиционните проекти със съществените изисквания към строежите, в съотв. с чл. 142, ал. 4 и ал. 5 от ЗУТ за проектите по процедура BG-RRP-4.023 „Подкрепа за устойчиво енергийно обновяване на жилищния сграден фонд – Етап I“ финансирана по НПВУ и да изпълнява функциите на строителен надзор , съгласно чл. 166 и чл. 168 от ЗУТ при изпълнението на СМР.,
Estimated Amount: 6 100.55
|
| Procedure 2 |
Subject to due process: Изготвяне на независима експертна оценка от сертифициран енергиен одитор съгласно чл.44, ал. 1 от Закона за енергийната ефективност (ЗЕЕ) след изпълнение на СМР по процедура BG-RRP-4.023 „Подкрепа за устойчиво енергийно обновяване на жилищния сграден фонд – Етап I“ финансирана по НПВУ,
Estimated Amount: 6 234.25
|
| Procedure 3 |
Subject to due process: Инженеринг - изготвяне на инвестиционен проект и извършване на СМР за внедряване на мерки за повишаване на енергийната ефективност на жилищна сграда, находяща се в гр. София, бул. "Васил Левски"№91 и ул. "Аксаков" №52,
Estimated Amount: 317 822.52
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN