Identification

UMIS Number BG-RRP-6.004-3722-C03
Project Name Investments in technological and ecological modernization in the farm of Emilian Lazov
Beneficiary 178503935 EMILIAN RUMENOV LAZOV
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 25.06.2024
Start Date 25.06.2024
End Date 30.06.2025
Status of Implementation of the Contract/Order of the Grant Contracted
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), Кюстендил (BG415), Невестино, с.Лиляч

Description

Brief description
Проектното предложение предвижда закупуване на земеделска техника за извършване на агротехнически мероприятия в стопанството на кандидата, доставка на линия за сортиране на череши и монтаж на фотоволтаична електро централа.
Activities
  • Activity: Инвестиции в технологична модернизация на стопанството на Емилиян Лазов: Предвижда се закупуването на следното оборудване: "ЛИНИЯ ЗА СОРТИРАНЕ НА ЧЕРЕШИ с минимални характеристики/ капацитет - 1 т. на час. Вана с елеватор Разделител (Дръжко-разчепкваща машина): Лента за качествен подбор Модул за сортиране Маса за пакетиране с врати и регулируем ъгъл Главно електрическо табло Инегриран хардуер със софгуер за анализ и мониторинг на данни за капацитет" , Contracted Amount: 282 672.83 , Reported Amount: 282 672.84

Participating Organizations

Partners
  • Partner: EMILIAN, Contracted Amount*: 0.00 , Reported Amount: 0.00
Contractors
  • Contractor: AGROMACHINA GROUP , Contracted Amount*: 0.00 , Reported Amount**: 26 893.95
  • Contractor: SAT 99 - A I P , Contracted Amount*: 72 092.16 , Reported Amount**: 72 092.16
  • Contractor: SORS M , Contracted Amount*: 183 686.72 , Reported Amount**: 183 686.73
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Award of grant agreements for support under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00
Indicator 2 Installed additional operational renewable energy capacity in MW, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.02 , Reached amount: 0.02
Indicator 3 Projects under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00

Financial Information

Total Project cost 282 672.84 EUR
Grant 141 336.42 EUR
Self amount 141 336.42 EUR
Total actual amounts paid 141 336.41 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN