Identification

UMIS Number BG-RRP-1.015-2247-C02
Project Name "School STEM Environment"
Beneficiary 000758835 OU "HRISTO SMIRNENSKI"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 20.09.2024
Start Date 20.09.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Област (BG412), Костенец, гр.Момин проход

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM на среда и : Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване.“, Contracted Amount: 91 982.89 , Reported Amount: 183 487.60

Participating Organizations

Partners None
Contractors
  • Contractor: "BESPOKE GROUP" EOOD, Contracted Amount*: 111 625.24 , Reported Amount**: 114 146.23
  • Contractor: DENIDA LTD, Contracted Amount*: 29 700.00 , Reported Amount**: 30 322.06
  • Contractor: KLETT BULGARIA, Contracted Amount*: 429.48 , Reported Amount**: 429.47
  • Contractor: Buildility EOOD, Contracted Amount*: 37 737.60 , Reported Amount**: 38 589.84
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 67.00 , Reached amount: 0.00

Financial Information

Total Project cost 92 902.72 EUR
Grant 92 902.72 EUR
Self amount 0.00 EUR
Total actual amounts paid 92 730.48 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: -, Estimated Amount: 0.00

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN