Identification

UMIS Number BG-RRP-1.015-1386-C02
Project Name "Technologies and entrepreneurship for exploring and protecting the environment"
Beneficiary 000673096 95 Secondary school "Professor Ivan Shishmanov"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 13.09.2024
Start Date 13.09.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Югозападен (BG41), София-Град (BG411), Столична, гр.София

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM център и ВОСКС в училище: Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване., Contracted Amount: 183 273.03 , Reported Amount: 92 490.98

Participating Organizations

Partners None
Contractors
  • Contractor: BARIONIKS EOOD, Contracted Amount*: 34 401.25 , Reported Amount**: 17 365.35
  • Contractor: BESPOUK GROUP EOOD, Contracted Amount*: 13 171.88 , Reported Amount**: 6 585.94
  • Contractor: STREZA Ltd, Contracted Amount*: 67 026.00 , Reported Amount**: 68 539.69
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 482.00 , Reached amount: 0.00

Financial Information

Total Project cost 185 105.76 EUR
Grant 185 105.76 EUR
Self amount 0.00 EUR
Total actual amounts paid 58 706.30 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Обществена поръчка по реда "събиране на оферти с обява" на осн. чл.103, ал. 1 от ЗОП, Estimated Amount: 0.00
  • Differentiated position 1: оферти
    Contractor: STREZA Ltd
    Contract total funded value: 67 026.00
Procedure 2 Subject to due process: Обява за събиране на оферти за обществена поръчка на стойност по чл. 20, ал. 3 или ал. 7 от ЗОП, Estimated Amount: 32 253.70
  • Differentiated position 1: Обява за събиране на оферти за обществена поръчка на стойност по чл. 20, ал. 3 или ал. 7 от ЗОП
    Contractor: BARIONIKS EOOD
    Contract total funded value: 34 401.25

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN