| UMIS Number | BG-RRP-6.004-3640-C02 |
| Project Name | Investments in technological and ecological modernization in the farm of ZP Marin Filchev |
| Beneficiary | 178120354 ZP Marin Filchev Marinov |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 06.06.2024 |
| Start Date | 06.06.2024 |
| End Date | 06.06.2025 |
| Status of Implementation of the Contract/Order of the Grant | Contracted |
| Location of Performance |
|
| Brief description |
Инвестициите по настоящото проектно предложение са пряко свързани с дейностите по първично селскостопанско производство на домати, лук, главесто зеле и дини и тяхното съхранение преди продажба. Инвестициите по проекта са: - хладилна инсталация за съхранение на плодове и зеленчуци, която ще се монтира в наличен цех в с. Флорентин -Трактор -Навигационна система -пръскачка -мулчер - изграждане на ФЕЦ за производство на електроенергия за покриване на собствените нужди в ПИ 76145.506.13, с.Флорентин, обл. Видин. Кандидатът е земеделски производител и отглежда върху собствени и наети площи около 15 дка домати, 8 дка лук, 40 дка главесто зеле, 25 дка дини, към които е насочена инвестицията и които стопанинът ще се задължи да отглежда в мониторинговия период. Инвестициите по настоящия проект представляват цялостна модернизация и нова стъпка в развитието на стопанството на ЗП Марин Филчев Маринов и ще допринесат за устойчивото и цифрово икономическо възстановяване на дружеството. |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Award of grant agreements for support under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 0.00 , Reached amount: 0.00 |
| Indicator 2 | Installed additional operational renewable energy capacity in MW, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.05 , Reached amount: 0.08 |
| Indicator 3 | Projects under the Fund to promote the technological and ecological transition of agriculture, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Total Project cost | 347 942.80 EUR |
| Grant | 173 971.40 EUR |
| Self amount | 173 971.40 EUR |
| Total actual amounts paid | 173 971.41 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка и изграждане на автономна фотоволтаична система за собствени нужди,
Estimated Amount: 88 884.00
|
| Procedure 2 |
Subject to due process: Доставка и инсталация на хладилна камера и хладилни панели,
Estimated Amount: 65 534.84
|
| Procedure 3 |
Subject to due process: Доставка на Трактор Kubota, пръскачка Kubota, Навигационна система и мулчер.,
Estimated Amount: 193 523.98
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN