| UMIS Number | BG-RRP-3.006-0406-C02 |
| Project Name | Instalation of new PV for own consumption in combination with battery |
| Beneficiary | 125019148 BMP-BLIZNATSI-METAL PLASTIK |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 10.11.2023 |
| Start Date | 10.11.2023 |
| End Date | 09.06.2025 |
| Status of Implementation of the Contract/Order of the Grant | Closed (completion date) |
| Location of Performance |
|
| Brief description |
БМП-БЛИЗНАЦИ-МЕТАЛ ПЛАСТИК ООД е с основна икономическа дейност- Код по КИД 2008: 24.54 Леене на други метали. Фирмата топи, лее и обработва цветни метали, предимно- алуминиеви сплави. Проектното предложение се отнася до подобряване на конкурентоспособноста на фирмата чрез инвестиции за изграждане на възобновяеми енергийни източници (ВЕИ) за собствено потребление, комбинирани с локални съоръжения за съхранение на енергия, с което да се насърчи прехода на частния сектор към екосъобразна дейност. БМП-БЛИЗНАЦИ-МЕТАЛ ПЛАСТИК ООД чрез проекта ще създаде условия за растеж и развитие на фирмата чрез значително намаляване разходите за електроенергия и намаляване себестойноста на продукцията която произвежда чрез основната си икономическа дейност. Фирмата чрез настоящия проект планира изграждане на фотоволтаична система върху покривa на производствените си сгради и урбанизираната земя в рамките на компанията, присъединени към електропреносната мрежа, с инсталирана мощност 200 kW за собствено потребление в комбинация със съоръжения за локално съхранение на произведената енергия - батерии. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Additional operational capacity installed for renewable energy, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.20 , Reached amount: 0.20 |
| Indicator 2 | Enterprises supported (of which small – including micro, medium, large), Measure Unit: enterprises, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00 |
| Indicator 3 | Capacity of installed storage facilities, Measure Unit: Number (kW), Base Value: 0.00 , Target amount: 204.80 , Reached amount: 204.80 |
| Total Project cost | 276 097.62 EUR |
| Grant | 138 048.81 EUR |
| Self amount | 138 048.81 EUR |
| Total actual amounts paid | 138 048.81 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Изграждане на Фотоволтаична система за производство на енергия от ВЕИ за собствено потребление в комбинации с локални съоръжения за съхранение на енергия (батерии) - 1бр. ,
Estimated Amount: 291 431.26
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN