| UMIS Number | BG-RRP-4.032-0126-C01 |
| Project Name | New capacity for electricity production from renewable sources, including LSS in "Progres" JSC |
| Beneficiary | 833067103 PROGRESS |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 10.11.2025 |
| Start Date | 10.11.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектът предвижда изграждане на локални съоръжения за съхранение на електрическа енергия (ЛСС) с инсталирана мощност от 1200 kW и минимален капацитет 2 580kWh, КТП и кабелна линия Ср.Н-20kV, разположени в УПИ C, ПИ 68850.523.5849 в кв.1303 по плана регулация и застрояване на гр.Стара Загора. Мощността на ЛСС ще бъде 46.87% от общата инсталирана мощност на фотоволтаичната централа . ЛСС ще бъде допълнение към проект на „Фотоволтаична електроцентрала с номинална инверторна мощност 2560kW находяща се в УПИ C, ПИ 68850.523.5849 в кв.1303 по плана регулация и застрояване на гр.Стара Загора “. Проектната разработка обхваща локални съоръжения за съхранение на електрическа енергия с мощност 1 200 kW и минимален капацитет 2 580 kWh, КТП и кабелна линия Ср.Н-20kV. Съгласно мощността 1 200 kW и минималния капацитет 2 580 kWh на съоръжения за съхранение на електрическа енергия, системата ще има полезен капацитет за продължителност на работа наи -малко 2ч. ( C-rate = 0.5C). Мощността на ЛСС - 1 200 kW, представлява 46.87% от общата мощност на фотоволтаичната централа – 2560kW, което е в допустимите граници от 30% до 50% от инсталираната мощност на фотоволтаичната централа, съгласно процедура BG-BG-RRP-4.032 "Подкрепа на нови мощности за производство на електроенергия от възобновяеми източници и съхранение на електроенергия с инсталирана мощност от 200 kW до 2 MW". |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 1.20 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 2.58 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 2.56 , Reached amount: 0.00 |
| Total Project cost | 1 070 459.08 EUR |
| Grant | 535 229.54 EUR |
| Self amount | 535 229.54 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка на материални активи - ЛСС,
Estimated Amount: 832 387.55
|
| Procedure 2 |
Subject to due process: Доставка на нематериални активи - Софтуер за управление на ЛСС,
Estimated Amount: 40 903.35
|
| Procedure 3 |
Subject to due process: Строително монтажни работи,
Estimated Amount: 65 677.99
|
| Procedure 4 |
Subject to due process: Съоръжения за свързване на ЛСС,
Estimated Amount: 49 706.69
|
| Procedure 5 |
Subject to due process: Услуги от инженерно-технически характер-авторски надзор,
Estimated Amount: 5 112.92
|
| Procedure 6 |
Subject to due process: Услуги от инженерно-технически характер-изготвяне на технически (работен проект),
Estimated Amount: 12 782.30
|
| Procedure 7 |
Subject to due process: Услуги от инженерно-технически характер-строителен надзор,
Estimated Amount: 10 737.12
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN