Identification

UMIS Number BG-RRP-1.015-1649-C01
Project Name Construction of a school STEM environment and high-tech equipped and connected classrooms (VOSKS) in Secondary school "Vasil Levski" - Krumovgrad, Kardzaly.
Beneficiary 108503741 Secondary school "Vasil Levski" - Krumovgrad, Kardzaly
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 25.09.2024
Start Date 25.09.2024
End Date 31.05.2026
Status of Implementation of the Contract/Order of the Grant In execution (starting date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Кърджали (BG425), Крумовград, гр.Крумовград

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM център и ВОСКС. : Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване., Contracted Amount: 183 114.97 , Reported Amount: 117 325.90

Participating Organizations

Partners None
Contractors
  • Contractor: Centar za tvorchesko obuchenie OOD, Contracted Amount*: 199 408.67 , Reported Amount**: 101 955.92
  • Contractor: DURAL OOD, Contracted Amount*: 30 061.05 , Reported Amount**: 15 369.98
  • Contractor: OT MARS OOD, Contracted Amount*: 71 841.16 , Reported Amount**: 0.00
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 132.00 , Reached amount: 0.00

Financial Information

Total Project cost 184 946.12 EUR
Grant 184 946.12 EUR
Self amount 0.00 EUR
Total actual amounts paid 118 303.62 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка на оборудване по обособена позиция № 1: "Доставка, монтаж и гаранционно обслужване на компютърно оборудване и периферия за СТЕМ център", Estimated Amount: 117 837.50
  • Differentiated position 1: ОП 1: "Доставка, монтаж и гаранционно обслужване на компютърно оборудване и периферия за СТЕМ център"
    Contractor: Centar za tvorchesko obuchenie OOD
    Contract total funded value: 141 001.84
Procedure 2 Subject to due process: Доставка на оборудване по обособена позиция № 2: "Доставка, монтаж и гаранционно обслужване на компютърно оборудване за ВОСКС, Estimated Amount: 58 406.83
  • Differentiated position 1: Доставка на оборудване по обособена позиция № 2: "Доставка, монтаж и гаранционно обслужване на компютърно оборудване за ВОСКС
    Contractor: Centar za tvorchesko obuchenie OOD
    Contract total funded value: 58 406.83
Procedure 3 Subject to due process: Обособена позиция №1: “Доставка, монтаж и гаранционно обслужване на маси, столове и мебели за сядане за обзавеждане на STEM център“, Estimated Amount: 66 446.71
  • Differentiated position 1: Обособена позиция №1: “Доставка, монтаж и гаранционно обслужване на маси, столове и мебели за сядане за обзавеждане на STEM център“
    Contractor: OT MARS OOD
    Contract total funded value: 71 841.16

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN