| UMIS Number | BG-RRP-4.032-0227-C01 |
| Project Name | "Construction of a local energy storage system (ESS) with an installed capacity of 0.4 MW and a storage capacity of 0,932 connected to a photovoltaic power plant with an installed capacity of 1 MW." |
| Beneficiary | 202521160 PM INVEST GROUP |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 06.03.2025 |
| Start Date | 06.03.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Предложението за изпълнение на инвестиция предвижда изграждане на локално съоръжение за съхранение на електроенергия (ЛСС) с мощност 0,4 МW и капацитет 0,932 MWh. Съоръжението ще бъде свързано към фотоволтаична инсталация с инсталирана AC мощност 1 MW на кандидата "ПМ Инвест Груп" ООД, разположена в поземлен имот в землището на с. Тетово, общ. Русе. С изграждането на системата за съхранение се цели максимизиране на употребата на електроенергия от фотоволтаичния парк. Дейността е съобразена с изискванията на принципа за „ненанасяне на значителни вреди“ върху околната среда и ще допринесе за екологичния преход на страната. Енергийният обект за производство на електрическа енергия от слънчева енергия предстои да бъде довършен и присъединен към съответната електрическа мрежа и отговаря на приложимите изисквания. Проектът ще осигури изграждане на локално съоръжение за съхранение на електроенергия (ЛСС) като част от комбиниран проект за създаване на нова мощност за производство на електрическа енергия от слънчева енергия и мощности за съхранение. Предвидените ЛСС, както и капацитетите по отношение на компонента за производство на електрическа енергия, отговарят на изискването за "нова мощност". |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.40 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 0.93 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 196 284.96 EUR |
| Grant | 98 142.48 EUR |
| Self amount | 98 142.48 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Проектиране, доставка, монтаж и въвеждане в експлоатация на ЛСС на електрическа енергия с мощност 400 КW и капацитет на съхранение 932 kWh към съществуваща ФВИ с мощност 0,99 MW, на обект находящ се в поземлен имот с идентификатор 72357.706.42, от ЗРП на с. Тетово, общ. Русе, обл. Русе,
Estimated Amount: 196 284.95
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN