| UMIS Number | BG-RRP-4.032-0261-C01 |
| Project Name | LSF Incotex jsc, Kotel |
| Beneficiary | 829054324 INCOTEX JSC |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 10.11.2025 |
| Start Date | 10.11.2025 |
| End Date | 31.03.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Създаване на локално съоръжение за съхранение на електрическа енергия към инсталирана ФЕЦ с мощност 1 MW в имот на Инкотекс АД, гр. Котел |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Installed and put into operation new capacities for electricity storage, Measure Unit: MW, Base Value: 0.00 , Target amount: 0.50 , Reached amount: 0.00 |
| Indicator 2 | Capacity of the installed storage, Measure Unit: MWh, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 3 | Installed and put into operation new capacities for the production of electricity from renewable energy (wind and/or solar energy), Measure Unit: MW, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Total Project cost | 437 665.84 EUR |
| Grant | 218 832.92 EUR |
| Self amount | 218 832.92 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 100.00 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Доставка и монтаж на ЛСС,
Estimated Amount: 820 000.00
|
| Procedure 2 |
Subject to due process: Изграждане на бетонов фундамент за поставяне на ЛСС,
Estimated Amount: 10 000.00
|
| Procedure 3 |
Subject to due process: Изграждане на кабелни връзки между ФЕЦ и ЛСС,
Estimated Amount: 4 000.00
|
| Procedure 4 |
Subject to due process: Разходи за програмен продукт за управление на ЛСС,
Estimated Amount: 0.00
|
| Procedure 5 |
Subject to due process: Свързване на ФЕЦ с ЛСС и настройка управление ЛСС,
Estimated Amount: 2 000.00
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN