| UMIS Number | BG-RRP-4.023-0755-C01 |
| Project Name | Implementation of energy renovation measures in a multi-family residential building No 212, residential complex "Sever", Pravets. |
| Beneficiary | 000776477 Municipality Pravets |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 22.10.2024 |
| Start Date | 22.10.2024 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проектното предложение предвижда енергийно обновяване на 2567.80 кв. м., чрез прилагане на следните мерки: 1. Топлоизолиране на външните стени на сградата; 2. Топлоизолиране на покрива на сградата 3. Топлоизолиране на под 4. Подмяна на дограма 5. Осигуряване на достъпна среда Реализирането на проекта има за цел, както следва: • подобряване енергийните характеристики на жилищни сгради, чрез прилагане на устойчиви интегрирани високоефективни енергийни мерки; • достигане на клас на енергопотребление „В“ след прилагане на енергоспестяващи мерки при многофамилните жилищни сгради; • намаление на енергийното потребление на страната, както и до редуциране на емисиите на парникови газове; • постигане на 30% спестяване на първична енергия за всеки обект от жилищния сграден фонд. • ресурсна ефективност, икономическа целесъобразност, устойчив строителен процес; • намаляване на енергийната бедност, чрез намаляване на разходите за енергия; • подобряване на условията и качеството за живот на населението в страната чрез технологично обновление и модернизиране на сградния фонд. |
| Activities |
|
| Partners |
|
| Contractors | None |
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Energy-efficiency renovation of residential buildings, Measure Unit: Renovated gross floor area of residential buildings (m2), Base Value: 0.00 , Target amount: 2 567.60 , Reached amount: 0.00 |
| Indicator 2 | Reduced greenhouse emissions, Measure Unit: Tones CO2, Base Value: 0.00 , Target amount: 86.60 , Reached amount: 0.00 |
| Indicator 3 | Reduction of the annual consumption of primary energy kWh/year., Measure Unit: kWh/година, Base Value: 629 294.19 , Target amount: 211 840.20 , Reached amount: 0.00 |
| Indicator 4 | % in primary non-renewable energy consumption, Measure Unit: %, Base Value: 0.00 , Target amount: 66.34 , Reached amount: 0.00 |
| Indicator 5 | Number of renovated housing units, Measure Unit: Number, Base Value: 0.00 , Target amount: 30.00 , Reached amount: 0.00 |
| Total Project cost | 429 382.71 EUR |
| Grant | 429 380.25 EUR |
| Self amount | 2.46 EUR |
| Total actual amounts paid | 0.00 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| There are no tender procedures |
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN