| UMIS Number | BG-RRP-4.023-2257-C02 |
| Project Name | Implementation of measures for increasing the energy efficiency of a residential building with administrative address Haskovo, "Stara planina" street, No. 18-20 and 22-24 |
| Beneficiary | 000903946 OBSHTINA HASKOVO |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 26.11.2024 |
| Start Date | 26.11.2024 |
| End Date | 30.06.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Проект "Въвеждане на мерки за повишаване на енергийната ефективност на жилищна сграда с адрес: гр. Хасково, ул."Стара планина", № 18-20 и 22-24" е насочен към изпълнение на местните политики за прилагане на устойчив модел на управление на сградния жилищен фонд на територията на град Хасково. Проектът е в съответствие с основната цел на процедура BG-RRP-4.023 по НПВУ и ще бъде реализиран чрез изпълнение на комплекс от мерки за енергийна ефективност. Сградата, обект на интервенция е частна собственост и за целта е сключено Споразумение за партньорство между Община Хасково и Сдружението на собствениците (краен получател) /регистрирани по реда на чл. 25, ал. 1 от ЗУЕС/. Проектът предвижда изпълнение на дейности за проектиране и извършване на СМР, включващи мерки за енергийна ефективност, предписани като задължителни за сградата в обследването за енергийна ефективност; съпътстващи строителни и монтажни работи, свързани с изпълнението на мерките за енергийна ефективност и съответното възстановяване на общите части на сградата в резултат на изпълнените мерки с енергоспестяващ ефект; СМР, които произтичат от нормативни изисквания, свързани с безопасната експлоатация на сградите и са предписани като задължителни в техническия паспорт на сградата, изграждане на достъпна среда и СМР, които са нормативно необходими за въвеждане на сградата в експлоатация. След изпълнение на предвидените мерките в многофамилната сграда ще се постигне клас на енергопотребление "В". ПИИ включва и дейности за осигуряване на качествено управление и организация на проекта, вкл. дейности за информация и комуникация. Предвидените дейности са съобразени с принципа за „ненанасяне на значителни вреди“, по смисъла на чл. 17 от Регламента за таксономията. При реализирането на настоящото ПИИ ще бъдат съблюдавани хоризонталните политики на Европейския съюз. |
| Activities |
|
| Partners |
|
| Contractors |
|
| Subcontractors |
|
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Energy-efficiency renovation of residential buildings, Measure Unit: Renovated gross floor area of residential buildings (m2), Base Value: 0.00 , Target amount: 3 365.00 , Reached amount: 0.00 |
| Indicator 2 | Reduced greenhouse emissions, Measure Unit: Tones CO2, Base Value: 0.00 , Target amount: 112.44 , Reached amount: 0.00 |
| Indicator 3 | Reduction of the annual consumption of primary energy kWh/year., Measure Unit: kWh/година, Base Value: 795 967.10 , Target amount: 263 864.97 , Reached amount: 0.00 |
| Indicator 4 | % in primary non-renewable energy consumption, Measure Unit: %, Base Value: 0.00 , Target amount: 66.85 , Reached amount: 0.00 |
| Indicator 5 | Number of renovated housing units, Measure Unit: Number, Base Value: 0.00 , Target amount: 20.00 , Reached amount: 0.00 |
| Total Project cost | 446 236.95 EUR |
| Grant | 445 993.58 EUR |
| Self amount | 243.37 EUR |
| Total actual amounts paid | 109 263.09 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Извършване на оценка на съответствието на инвестиционните проекти и извършване на строителен надзор на обект "Въвеждане на мерки за енергийна ефективност на жилищна сграда с адрес гр. Хасково, ул. Стара планина №18-20 и 22-241",
Estimated Amount: 8 877.77
|
| Procedure 2 |
Subject to due process: Изготвяне на независима експертна оценка,
Estimated Amount: 2 064.60
|
| Procedure 3 |
Subject to due process: Инжинеринг на обект "Въвеждане на мерки за енергийна ефективност на жилищна сграда с адрес гр. Хасково, ул. Стара планина №18-20 и 22-24",
Estimated Amount: 422 335.06
|
| Procedure 4 |
Subject to due process: Прилагане на мерки за публичност и информация,
Estimated Amount: 2 300.81
|
Notes: