| UMIS Number | BG-RRP-13.009-0220-C01 |
| Project Name | Installation of photovoltaic systems (PV) in existing social services, state-delegated activity and purchase of an electric vehicle, including a connected charging station for the provision of social services in the Municipality of Pomorie |
| Beneficiary | 000057179 Pomorie municipality |
| Funding | RRF ==> Recovery and Resilience Plan |
| Date of the Contract/Order | 18.11.2025 |
| Start Date | 18.11.2025 |
| End Date | 17.08.2026 |
| Status of Implementation of the Contract/Order of the Grant | In execution (starting date) |
| Location of Performance |
|
| Brief description |
Настоящото предложение за изпълнение на инвестиции включва дейности по инсталиране на фотоволтаични системи (ФЕЦ) в съществуващи социални услуги, делегирана от държавата дейност - Център за обществена подкрепа гр. Поморие и Център за настаняване от семеен тип за деца и младежи с увреждания гр. Поморие, както и закупуване на електрическо превозно средство, включително свързана зарядна станция за предоставяне на социални услуги в Община Поморие. Целта на предвидените в проекта инвестиции е да се повиши енергийната ефективност, да се намали енергийната зависимост и да се подобри оперативната устойчивост в сектора на социалните услуги чрез два допълващи се компонента/дейности: инсталиране на фотоволтаични системи в общински социални услуги и предоставяне на електрически превозни средства в подкрепа на социалната дейност. Това ще доведе до намаляване зависимостта от изкопаеми горива, насърчаване на производството на възобновяема енергия и подпомагане на прехода към чиста мобилност в съответствие с Плана REPowerEU, Европейската соларна стратегия и Зеления пакт на ЕС. |
| Activities |
|
| Partners | None |
| Contractors |
|
| Subcontractors | None |
| Members of the Consortium | None |
|
Notes: * The projected contract value may be lower than the reported one because of any of the following reasons:
** This column represents the amount of costs claimed by the beneficiary |
|
| Indicator 1 | Purchased electric vehicles and connected charging stations, each with a minimum power of 22 kW, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 0.00 |
| Indicator 2 | Number of social services with installed PV power plants with a capacity of 15 to 30 kW, Measure Unit: Number, Base Value: 0.00 , Target amount: 2.00 , Reached amount: 0.00 |
| Total Project cost | 118 528.05 EUR |
| Grant | 118 528.05 EUR |
| Self amount | 0.00 EUR |
| Total actual amounts paid | 60 313.44 EUR |
| Percentage of EU co-financing | 83.33 % |
| None | |
|
Notes: 1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower. 2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment. |
|
| Procedure 1 |
Subject to due process: Закупуване на електрическо превозно средство и свързана зарядна станция за целите на предоставяне на социални услуги в Община Поморие,
Estimated Amount: 48 402.30
|
| Procedure 2 |
Subject to due process: Инсталиране на фотоволтаични системи в съществуващи сгради за социални услуги на територията на община Поморие по две обособени позиции,
Estimated Amount: 25 754.32
|
Notes:
All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN