Identification

UMIS Number BG-RRP-1.015-0860-C02
Project Name "School STEM Environment"
Beneficiary 829091529 OU "Dimitar Kamburov"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 19.07.2024
Start Date 19.07.2024
End Date 13.03.2026
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Югоизточен (BG34), Сливен (BG342), Котел, с.Стрелци

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на училищен STEM център и ВОСКС: Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване.“, Contracted Amount: 30 665.48 , Reported Amount: 61 330.48

Participating Organizations

Partners None
Contractors
  • Contractor: A1 Bulgaria EAD, Contracted Amount*: 25 511.42 , Reported Amount**: 51 022.84
  • Contractor: Now-A stroi ltd, Contracted Amount*: 5 153.82 , Reported Amount**: 10 307.64
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 6.00 , Reached amount: 6.00

Financial Information

Total Project cost 30 920.79 EUR
Grant 30 920.79 EUR
Self amount 0.00 EUR
Total actual amounts paid 30 920.78 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN