Identification

UMIS Number BG-RRP-1.015-1238-C02
Project Name Building a school STEM environment in Sports School "St. Kliment Ohridski"
Beneficiary 000186252 Sports School "St. Kliment Ohridski"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 17.09.2024
Start Date 17.09.2024
End Date 08.04.2026
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Северна и югоизточна България (BG3), Северозападен (BG31), Враца (BG313), Враца, гр.Враца

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Изграждане на STEM център и ВОСКС в училище: Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване., Contracted Amount: 92 031.52 , Reported Amount: 183 800.88

Participating Organizations

Partners None
Contractors
  • Contractor: MI BAU, Contracted Amount*: 66 597.20 , Reported Amount**: 68 100.02
  • Contractor: BALLISTIC CELL EOOD, Contracted Amount*: 113 145.60 , Reported Amount**: 115 700.86
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 26.00 , Reached amount: 26.00

Financial Information

Total Project cost 92 763.42 EUR
Grant 92 763.42 EUR
Self amount 0.00 EUR
Total actual amounts paid 92 763.42 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

Procedure 1 Subject to due process: Доставка и монтаж на мебели, Estimated Amount: 19 580.85
  • Differentiated position 1: Доставка и монтаж на мебели
    Contractor: MI BAU
    Contract total funded value: 19 580.85
Procedure 2 Subject to due process: Доставка, монтаж и въвеждане в експлоатация на оборудване за изграждане на STEM център в Спортно училище „Св. Кл. Охридски“, гр. Враца, Estimated Amount: 94 501.65
  • Differentiated position 1: Доставка, монтаж и въвеждане в експлоатация на оборудване за изграждане на STEM център в Спортно училище „Св. Кл. Охридски“, гр. Враца
    Contractor: BALLISTIC CELL EOOD
    Contract total funded value: 113 145.60
Procedure 3 Subject to due process: Извършване на СМР дейности, Estimated Amount: 47 016.35
  • Differentiated position 1: Извършване на СМР дейности
    Contractor: MI BAU
    Contract total funded value: 47 016.35

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN