Identification

UMIS Number BG-RRP-1.015-0967-C02
Project Name Building school STEM environmentand high-tech equipped and connected classrooms
Beneficiary 000342388 OSNOVNO UCHILISHTE "VASIL APRILOV"
Funding RRF ==> Recovery and Resilience Plan
Date of the Contract/Order 20.09.2024
Start Date 20.09.2024
End Date 22.12.2025
Status of Implementation of the Contract/Order of the Grant Closed (completion date)
Location of Performance
  • България, Югозападна и южно-централна България (BG4), Южен централен (BG42), Пазарджик (BG423), Пазарджик, с.Синитово

Description

Brief description
Изграждане на училищна STEM среда и високотехнологични оборудвани и свързани класни стаи (ВОСКС).
Activities
  • Activity: Дейност 1: Изграждане на STEM център и ВОСКС в училище: Дейността е детайлно описана в Концепция за изграждане на училищна STEM среда (Приложение II към Поканата), подписана с електронен подпис от директора на училището (или оправомощено от него лице) и от директора на Националния STEM център (или оправомощено от него лице) и прикачена в секция 12 от Формуляра за кандидатстване., Contracted Amount: 30 631.86 , Reported Amount: 61 251.54

Participating Organizations

Partners None
Contractors
  • Contractor: Supernova engineering, Contracted Amount*: 11 487.24 , Reported Amount**: 22 974.48
  • Contractor: MAIV BUILD , Contracted Amount*: 19 138.53 , Reported Amount**: 38 277.06
Subcontractors None
Members of the Consortium None

Notes:

* The projected contract value may be lower than the reported one because of any of the following reasons:

  • For physical person, the contracted value does not include the employer expenses, which are admissible expenses and are accounted under the project
  • The Beneficiary has reported expense only with an invoice without a contract with the selected contractor
  • The beneficiary has reported over again expenses to the MA

** This column represents the amount of costs claimed by the beneficiary

Indicators

Indicator 1 Schools with newly built and/or equipped STEM laboratories, including high-tech, Measure Unit: Number, Base Value: 0.00 , Target amount: 1.00 , Reached amount: 1.00
Indicator 2 Classroom capacity of new or modernised childcare and education facilities, Measure Unit: persons, Base Value: 0.00 , Target amount: 36.00 , Reached amount: 36.00

Financial Information

Total Project cost 30 881.00 EUR
Grant 30 881.00 EUR
Self amount 0.00 EUR
Total actual amounts paid 30 880.99 EUR
Percentage of EU co-financing 100.00 %

Financial Corrections

None

Notes:

1 The quoted value represents the maximum amount of the imposed financial correction. Depending on the performance of the contract, the actual amount of the deducted financial correction may be lower.

2 A financial correction with a zero total value means that it has been canceled as a result of a court judgment.

Procurements

There are no tender procedures

Notes:

All amounts are in euro (EUR) / 1 EUR = 1,95583 BGN